# 2025-02518: New Ohio River Hydro Project Application Submitted

2025-02518, Ohio Power and Light, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-02-12, effective Deadline for filing additional study requests and requests for cooperating agency status: March 24, 2025. (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-02518
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-02518
- Title: Ohio Power and Light, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 9425
- Published: 2025-02-12
- Effective: Deadline for filing additional study requests and requests for cooperating agency status: March 24, 2025.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

New Ohio River Hydro Project Application Submitted

## Summary

Ohio Power and Light, LLC has applied for a big new license to build a hydroelectric project at the Robert C. Byrd Locks and Dam on the Ohio River. This project could change how power is made in Mason County, West Virginia, and folks have until March 24, 2025, to ask for extra studies or get involved. It’s a chance to help shape clean energy and possibly impact local land and water use.

## Effects PRIA read

- Chance to Request Extra Scientific Studies: benefit, low. If you (a resource agency, Indian Tribe, or person) believe an additional scientific study is needed, you must file a request with the Commission by March 24, 2025 to ask for that study and serve a copy on the applicant.
- New Hydropower Project Proposed in West Virginia: mixed, medium. Ohio Power and Light, LLC seeks a major license to build the Robert C. Byrd Locks and Dam Hydroelectric Project in Mason County, West Virginia, that would occupy about 16 acres of Corps-managed Federal land, include two powerhouses and a 2.5-mile, 69-kilovolt transmission line, and is projected to…
- Office of Public Participation Can Help Locals: benefit, low. FERC's Office of Public Participation can help landowners, community organizations, Tribal members, and others access information and get assistance with filings such as interventions, comments, or requests for rehearing; OPP contact is (202) 502-6595 or [email protected].
- Key Licensing Timeline Dates for Stakeholders: benefit, low. FERC lists target dates for processing the application: possible deficiency or information requests in March 2025, an acceptance letter in July 2025, Scoping Document 1 for comments in August 2025, and a Notice of Ready for Environmental Analysis in October 2025.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-02518 on federalregister.gov](https://www.federalregister.gov/documents/2025/02/12/2025-02518/ohio-power-and-light-llc-notice-of-application-tendered-for-filing-with-the-commission-and)
- [2025-02518 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-02-12/pdf/2025-02518.pdf)

## Related
- [Previous: 2025-02517, Pacific Gas & Electric Company; Notice of Application for Temporary Flow Modifi…](https://policyrisk.com/federal-register/2025-02517)
- [Next: 2025-02519, Third Party Contracting Guidance; Delay of Applicability Date](https://policyrisk.com/federal-register/2025-02519)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-02518 (as of 2026-06-08).