# 2025-02778: Hydro Power Renewal: Edison's Big Ask on Federal Turf

2025-02778, Southern California Edison Company; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests Establishing Procedural Schedule for Relicensing and Deadline for Submission of Final Amendments, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-02-19, effective Deadline for filing additional study requests and requests for cooperating agency status: March 31, 2025. Preliminary procedural milestones include: Issue Scoping Document 1 for comments (June 2025); Issue Acceptance Letter (July 2025); Issue Notice of Ready for Environmental Analysis (August 2025). (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-02778
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-02778
- Title: Southern California Edison Company; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests Establishing Procedural Schedule for Relicensing and Deadline for Submission of Final Amendments
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 9898
- Published: 2025-02-19
- Effective: Deadline for filing additional study requests and requests for cooperating agency status: March 31, 2025. Preliminary procedural milestones include: Issue Scoping Document 1 for comments (June 2025); Issue Acceptance Letter (July 2025); Issue Notice of Ready for Environmental Analysis (August 2025).
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Hydro Power Renewal: Edison's Big Ask on Federal Turf

## Summary

Southern California Edison is asking to renew the license for its Lee Vining Hydroelectric Project in California, which affects 536 acres of federal land. The government is inviting people and agencies to request extra studies or join the process by March 31, 2025. This sets the stage for careful review and planning, impacting local communities and the environment while keeping the power flowing.

## Effects PRIA read

- Public deadlines to request studies: benefit, low. If you or your agency want extra scientific studies or to be a cooperating agency for the Lee Vining Project relicensing, you must file a study request or cooperating agency request by March 31, 2025. The application was filed January 29, 2025, and the Commission instructs requests be filed within…
- New major license application filed: mixed, medium. Southern California Edison filed an application for a New Major License for the Lee Vining Hydroelectric Project (Project No. 1388-082) on January 29, 2025. The existing project is located on Lee Vining and Glacier Creeks in Inyo County, California and affects 536 acres of Federal land managed by t…
- Applicant not proposing operational changes: mixed, low. Southern California Edison states it is not proposing any changes to project facilities or operation as part of this relicensing application. That means the company intends to request a new license without proposing alterations to how the project is currently built or operated.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-02778 on federalregister.gov](https://www.federalregister.gov/documents/2025/02/19/2025-02778/southern-california-edison-company-notice-of-application-tendered-for-filing-with-the-commission-and)
- [2025-02778 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-02-19/pdf/2025-02778.pdf)

## Related
- [Previous: 2025-02776, Combined Notice of Filings #1](https://policyrisk.com/federal-register/2025-02776)
- [Next: 2025-02781, Product Change-Priority Mail and USPS Ground Advantage® Negotiated Service Agre…](https://policyrisk.com/federal-register/2025-02781)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-02778 (as of 2026-06-08).