2025-03496, Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Warrior Hydro, LLC, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-03-05, effective Deadline for filing comments, motions to intervene, competing applications, or notices of intent: 60 days from the issuance of this notice. (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-03496
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-03496
- Title: Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Warrior Hydro, LLC
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 11307
- Published: 2025-03-05
- Effective: Deadline for filing comments, motions to intervene, competing applications, or notices of intent: 60 days from the issuance of this notice.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Alabama Hydro Project Locks In for Federal Review and Comments

## Summary

Warrior Hydro, LLC wants to study building a new hydropower project at the William Bacon Oliver Lock and Dam in Alabama. This project could generate clean energy but needs approval first, and the public has 60 days to share their thoughts or compete with other applications. If approved, it could bring new power and jobs to the area without any immediate costs or land changes yet.

## Effects PRIA read

- Permit Won't Allow Entry or Land Work: benefit, low. A preliminary permit only gives someone priority to file a license application; it does not let the permit holder do land‑disturbing activities or enter lands or waters owned by others without the owner's express permission. That means landowners are not required to allow access just because a perm…
- Project Adds 9.6 MW / 37,000 MWh: benefit, medium. The proposed Oliver Hydropower Project would have a total installed capacity of 9.6 megawatts and an estimated annual generation of 37,000 megawatt‑hours, plus a 0.9‑mile, 34.5 kV transmission line. If built, it would add local electricity supply near Tuscaloosa, Alabama.
- Permit Gives Developer Priority to File License: benefit, low. The sole purpose of a preliminary permit is to give the permit holder priority to file a license application during the permit term. The permit does not by itself allow construction or entry onto others' land.
- FERC Office Offers Help to Landowners and Tribes: benefit, low. The Commission's Office of Public Participation (OPP) can help members of the public—including landowners, community organizations, and Tribal members—access information and navigate Commission processes such as filing comments or interventions. OPP provides contact help and filing assistance.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-03496 on federalregister.gov](https://www.federalregister.gov/documents/2025/03/05/2025-03496/notice-of-preliminary-permit-application-accepted-for-filing-and-soliciting-comments-motions-to)
- [2025-03496 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-03-05/pdf/2025-03496.pdf)

## Related
- [Previous: 2025-03495, Agency Information Collection Activities; Extension, Without Change, of a Curre…](https://policyrisk.com/federal-register/2025-03495)
- [Next: 2025-03497, Ketchikan Public Utilities; Notice of Section 106 Meeting](https://policyrisk.com/federal-register/2025-03497)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-03496 (as of 2026-06-08).