## Facts
- Document number: 2025-08403
- Title: In the Matter of Patriot Engineering and Environmental, Inc.; Confirmatory Order Modifying License
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 90 FR 20322
- Published: 2025-05-13
- Effective: 2025-04-25
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-10-19

## In one line

NRC Orders Engineering Firm to Track Its Missing Moisture Gauge

## Summary

The Nuclear Regulatory Commission made Patriot Engineering and Environmental, Inc. promise to fix safety slip-ups after losing a moisture gauge in 2023. They agreed to better track their gauges, label them clearly, train their staff, and set clear safety roles—all starting right away. This keeps everyone safer and avoids future fines or problems.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) is issuing a Confirmatory Order to Patriot Engineering and Environmental, Inc., to memorialize the agreement reached during an alternative dispute resolution mediation session held on February 18, 2025. The Confirmatory Order contains commitments made to resolve three apparent violations of NRC requirements relating to the loss and subsequent recovery of portable moisture density gauge on November 15, 2023. The commitments include actions by Patriot Engineering and Environmental, Inc., to establish roles and responsibilities for site radiation safety officers, develop and implement an inspection program of gauge users, label gauges with licensee contact information, use tracking devices to monitor the location of the gauges, and develop a training program for gauge users and site radiation safety officers. The Confirmatory Order is effective upon issuance.

## Effects PRIA read

- Install tracking devices on all gauges: cost, medium. Patriot must affix a tracking device to every gauge it currently owns within 90 days of April 25, 2025, and must affix tracking devices to every gauge procured after that date before using it in the field. The company must keep records showing devices were installed for five years for gauges procur…
- New required training and annual practical exams: benefit, medium. Patriot must develop initial and annual refresher training for all technicians and site radiation safety officers within one year of April 25, 2025, with the training implemented beginning in calendar year 2026. Each gauge user must pass a practical examination at intervals not to exceed one year,…
- Yearly job-performance inspections for gauge users: cost, medium. Within one year of April 25, 2025, Patriot must implement an inspection program that observes each active gauge user's job performance at actual temporary job sites at intervals not to exceed one year. The inspections must be conducted by the corporate or site RSO (or by a formally trained individu…
- Photographic proof and two physical controls required: cost, low. Within one year of April 25, 2025, Patriot must require gauge users to provide photographic evidence to the corporate or site RSO showing that gauges are locked, secured against shifting during transport, and secured with a minimum of two independent physical controls whenever not under constant su…
- Stickers with RSO contact info for public: benefit, low. Within six months of April 25, 2025, Patriot must place legible stickers with corporate and site radiation safety officer contact information on all gauge cases and gauges, and must update those stickers within 60 days when contact information changes. This is intended to let members of the public…
- Independent third‑party safety audit required: cost, medium. Within three years of April 25, 2025, Patriot must complete an independent third‑party audit of its radiation safety program that reviews implementation of the items in the Order and covers at least 50 percent of the facilities listed on the license. Patriot must keep records showing completion of…
- NRC agrees not to pursue penalties if commitments met: benefit, medium. As part of the agreement effective April 25, 2025, the NRC will not pursue further enforcement action, issue a notice of violation, or propose a civil penalty related to the apparent violations in Inspection Report 03037878/2023001 if Patriot completes the commitments. The NRC will also refrain for…

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2025-08403 on federalregister.gov](https://www.federalregister.gov/documents/2025/05/13/2025-08403/in-the-matter-of-patriot-engineering-and-environmental-inc-confirmatory-order-modifying-license)
- [2025-08403 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-05-13/pdf/2025-08403.pdf)

## Related
- [Previous: 2025-08402, Pacific Fishery Management Council; Public Meeting](https://policyrisk.com/federal-register/2025-08402)
- [Next: 2025-08404, Appointment of Members of Senior Executive Service Performance Review Board](https://policyrisk.com/federal-register/2025-08404)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-08403 (as of 2026-10-19).