2025-08949, Notice of Intent To Amend the Resource Management Plan for the Robinson Summit Substation Expansion and 525kV Interconnection Project and Prepare an Associated Environmental Assessment, is a Federal Register notice from Interior Department, Land Management Bureau published 2025-05-20, effective 2025-06-20; PRIA reads it as touching household money (as of 2026-10-21).

- Canonical: https://policyrisk.com/federal-register/2025-08949
- As of: 2026-10-21
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-08949
- Title: Notice of Intent To Amend the Resource Management Plan for the Robinson Summit Substation Expansion and 525kV Interconnection Project and Prepare an Associated Environmental Assessment
- Type: Notice
- Agencies: Interior Department; Land Management Bureau
- Citation: 90 FR 21506
- Published: 2025-05-20
- Effective: 2025-06-20
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-10-21

## In one line

Nevada Power Line Expansion Triggers a Land-Use Planning Update

## Summary

The Bureau of Land Management is planning to update the resource management plan for the Robinson Summit Substation Expansion and a new 525kV power line connection in Nevada. They’re asking the public to share ideas and concerns by June 20, 2025, to help shape the project’s environmental review. This update aims to support better energy infrastructure while protecting the land and community interests.

## Abstract

In compliance with the National Environmental Policy Act of 1969, as amended (NEPA), and the Federal Land Policy and Management Act of 1976, as amended (FLPMA), the Bureau of Land Management (BLM, we) Nevada State Director intends to prepare a resource management plan (RMP) amendment with an associated environmental assessment (EA) for the Robinson Summit Substation Expansion and 525 kV Interconnection Project (Project). This notice is announcing the beginning of the scoping period to solicit public comments and identify issues and alternatives. It is also providing the planning criteria for public review.

## Effects PRIA read

- BLM to consider utility corridor and 525 kV line: benefit, low. The BLM intends to amend the Ely District Resource Management Plan to consider a designated utility corridor on about 307 acres of public land in White Pine County, Nevada. The Project would include a 50-acre expansion of the Robinson Summit Substation, a new 1.3-mile single-circuit 525 kV transmis…
- Public scoping and comment deadline: benefit, low. You can submit comments on the scope, issues, and alternatives for this RMP amendment and environmental assessment by June 20, 2025, or within 15 days after the last public meeting, whichever is later. The BLM will hold at least one public scoping meeting in Ely, Nevada, with meeting dates announce…
- Tribal government-to-government consultation: benefit, low. The BLM will consult with Indian Tribal Nations on a government-to-government basis in accordance with Executive Order 13175 and BLM policy, and will give due consideration to tribal concerns including impacts on Indian trust assets and cultural resources. Federal, State, local agencies and Tribes…
- ACEC nominations excluded from this process: cost, low. The BLM states that the scope of this land use planning process does not include addressing the evaluation or designation of Areas of Critical Environmental Concern (ACEC), and BLM is not considering ACEC nominations as part of this process. That means ACEC nominations will not be evaluated through…

## Related documents

- [2026-18261](https://policyrisk.com/federal-register/2026-18261): National Petroleum Reserve in Alaska Production Site Development, 2026-09-08
- [2026-12738](https://policyrisk.com/federal-register/2026-12738): Royalty for Oil and Gas Lost From Onshore Federal and Indian Leases, 2026-06-24
- [2026-12734](https://policyrisk.com/federal-register/2026-12734): Oil and Gas Leasing, 2026-06-24
- [2026-09386](https://policyrisk.com/federal-register/2026-09386): Rescission of Conservation and Landscape Health Rule, 2026-05-12
- [2026-09387](https://policyrisk.com/federal-register/2026-09387): Revision of Regulations for Grazing Administration, Exclusive of Alaska, 2026-05-12
- [2026-20020](https://policyrisk.com/federal-register/2026-20020): Agency Information Collection Activities; Submission to the Office of Management and Budget for Review and Approval; Resource Management Pl…, 2026-09-30

## Sources
- [2025-08949 on federalregister.gov](https://www.federalregister.gov/documents/2025/05/20/2025-08949/notice-of-intent-to-amend-the-resource-management-plan-for-the-robinson-summit-substation-expansion)
- [2025-08949 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-05-20/pdf/2025-08949.pdf)

## Related
- [Previous: 2025-08948, Agency Information Collection Activity: Loan Analysis](https://policyrisk.com/federal-register/2025-08948)
- [Next: 2025-08950, Combined Notice of Filings #1](https://policyrisk.com/federal-register/2025-08950)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-08949 (as of 2026-10-21).