# 2025-11304: St. Louis Ozone Trouble Gets Officially Upgraded to Serious

2025-11304, Finding of Failure To Attain for the Missouri Portion of the St. Louis Nonattainment Area for the 2015 Ozone National Ambient Air Quality Standards, is a Federal Register proposed rule from Environmental Protection Agency published 2025-06-20, effective 2024-12-31; PRIA reads it as touching household money (as of 2026-11-03).

- Canonical: https://policyrisk.com/federal-register/2025-11304
- As of: 2026-11-03
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-11304
- Title: Finding of Failure To Attain for the Missouri Portion of the St. Louis Nonattainment Area for the 2015 Ozone National Ambient Air Quality Standards
- Type: Proposed Rule
- Agencies: Environmental Protection Agency
- Citation: 90 FR 26240
- Published: 2025-06-20
- Effective: 2024-12-31
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-03

## In one line

St. Louis Ozone Trouble Gets Officially Upgraded to Serious

## Summary

The Missouri part of the St. Louis area didn’t meet the 2015 ozone air quality standards on time, so it’s now officially labeled as a “Serious” pollution problem. This means tougher rules and cleanup plans will kick in to help clear the air. Residents and businesses should watch for new deadlines and possible costs as the EPA works to fix the problem, with public comments open until July 21, 2025.

## Abstract

The Environmental Protection Agency (EPA) is accepting comment on a determination that the Missouri portion of the St. Louis, MO-IL bi-state nonattainment area failed to attain the 2015 8-hour ozone National Ambient Air Quality Standards (NAAQS) by the applicable attainment date. The effect of failing to attain by the applicable attainment date is that the area is reclassified by operation of law to "Serious" nonattainment for the 2015 ozone NAAQS. On November 25, 2024, the EPA published a final action in the Federal Register which determined that the St. Louis area failed to attain the 2015 ozone NAAQS by the Moderate area attainment date. That action also reclassified the area to Serious by operation of law with an effective date of December 31, 2024. On January 24, 2025, the EPA received a petition for reconsideration of that final action from the State of Missouri. On March 5, 2025, EPA Region 7 granted the petition for reconsideration and stated our intention to undergo a notice and comment rulemaking. Therefore, the EPA is accepting comment on the determination that the St. Louis area failed to attain by the attainment date. The Illinois portion of the St. Louis, MO-IL bi-state area is addressed separately.

## Effects PRIA read

- St. Louis reclassified to "Serious": cost, medium. The Missouri portion of the St. Louis nonattainment area was reclassified to "Serious" for the 2015 ozone standard effective December 31, 2024. The area must attain the 2015 ozone NAAQS as expeditiously as practicable but no later than August 3, 2027.
- Major source permitting thresholds lowered to 50 tpy: cost, high. As a result of the Serious reclassification, major source applicability thresholds are now 50 tons per year (tpy) for volatile organic compounds (VOC) and nitrogen oxides (NOX). This changes which stationary sources are considered "major" for permitting in the Missouri portion of the St. Louis area.
- Emission offset ratio set at 1.20 to 1: cost, high. For new or modified major stationary sources subject to review under Missouri regulation 10 CSR 10-6.060 (EPA-approved SIP), VOC and NOX emission increases must be offset by emission reductions at a minimum ratio of 1.20 to 1.
- Missouri must submit Serious-area SIP revisions: cost, medium. Missouri must submit State Implementation Plan (SIP) revisions that satisfy the statutory and regulatory requirements for Serious areas and follow SIP submission and control-measure implementation deadlines established for newly reclassified areas (see 40 CFR 51.1402). These SIP revisions are inten…
- Determination itself imposes no new immediate requirements: benefit, low. The EPA states that this determination (and the rulemaking accepting comment on it) does not, by itself, impose any new requirements on small entities or create new information-collection burdens. The reclassification, however, triggers statutory obligations that lead to later requirements.

## Related documents

- [2026-22082](https://policyrisk.com/federal-register/2026-22082): Additional Reconsideration Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sour…, 2026-10-29
- [2026-21155](https://policyrisk.com/federal-register/2026-21155): Renewable Fuel Standard (RFS) Program: Reallocation of Additional 2025 Small Refinery Exemptions, 2026-10-16
- [2026-20849](https://policyrisk.com/federal-register/2026-20849): Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy, 2026-10-13
- [2026-19071](https://policyrisk.com/federal-register/2026-19071): Partial Repeal of the Carbon Pollution Standards for Fossil Fuel-Fired Electric Generating Units, 2026-09-17
- [2026-19072](https://policyrisk.com/federal-register/2026-19072): Rescission of the Greenhouse Gas Findings for Fossil Fuel-Fired Power Plants and Repeal of Regulations for Power Plant Greenhouse Gas Emiss…, 2026-09-17
- [2026-18317](https://policyrisk.com/federal-register/2026-18317): Updated Definition of “Waters of the United States”, 2026-09-09

## Sources
- [2025-11304 on federalregister.gov](https://www.federalregister.gov/documents/2025/06/20/2025-11304/finding-of-failure-to-attain-for-the-missouri-portion-of-the-st-louis-nonattainment-area-for-the)
- [2025-11304 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-06-20/pdf/2025-11304.pdf)

## Related
- [Previous: 2025-11281, Air Plan Approval; California; Eastern Kern Air Pollution Control District; Sta…](https://policyrisk.com/federal-register/2025-11281)
- [Next: 2025-11326, Air Plan Approval; Guam; Clean Data Determination for the Piti-Cabras Nonattain…](https://policyrisk.com/federal-register/2025-11326)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-11304 (as of 2026-11-03).