# 2025-11786: Tennessee Gas Wants More Time Under an Existing Safety Exception

2025-11786, Pipeline Safety: Request for Special Permit, is a Federal Register notice from Transportation Department, Pipeline and Hazardous Materials Safety Administration published 2025-06-26, effective Submit any comments regarding this special permit request by July 28, 2025. The active special permit PHMSA-2019-0152 was granted on March 30, 2023 and is effective until March 30, 2033 for the described segment.; PRIA reads it as touching household money (as of 2026-11-05).

- Canonical: https://policyrisk.com/federal-register/2025-11786
- As of: 2026-11-05
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-11786
- Title: Pipeline Safety: Request for Special Permit
- Type: Notice
- Agencies: Transportation Department; Pipeline and Hazardous Materials Safety Administration
- Citation: 90 FR 27385
- Published: 2025-06-26
- Effective: Submit any comments regarding this special permit request by July 28, 2025. The active special permit PHMSA-2019-0152 was granted on March 30, 2023 and is effective until March 30, 2033 for the described segment.
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-05

## In one line

Tennessee Gas Wants More Time Under an Existing Safety Exception

## Summary

Tennessee Gas Pipeline Company, part of Kinder Morgan, is asking for a special permit to skip some pipeline safety rules for a bit longer. The government wants your thoughts on this by July 28, 2025, before deciding. This affects pipeline safety rules but won’t cost the public extra money right now.

## Abstract

PHMSA is publishing this notice to solicit public comments on a request for one (1) special permit segment extension submitted by Tennessee Gas Pipeline Company, LLC (TGP), a subsidiary of Kinder Morgan, Inc. TGP is seeking relief from compliance with certain requirements in the Federal pipeline safety regulations. At the conclusion of the 30-day comment period, PHMSA will review the comments received from this notice as part of its evaluation to grant or deny the special permit request.

## Effects PRIA read

- Special permit extension adds 732 feet: cost, low. Tennessee Gas Pipeline Company (TGP) asked to add 732 feet (about 0.139 miles) to an existing special permit segment so the permit would cover a total of 3,562 feet (about 0.675 miles) of pipeline in Barren County, Kentucky. The active special permit (PHMSA-2019-0152), granted March 30, 2023 and ef…
- PHMSA finds no significant environmental impacts: benefit, low. PHMSA reviewed the Final Environmental Assessment (FEA) for the requested segment extension and found that expanding the special permit would not result in significant impacts to the human environment. PHMSA concluded the existing FEA and Finding of No Significant Impact remain adequate and that no…

## Related documents

- [2026-22396](https://policyrisk.com/federal-register/2026-22396): Pipeline Safety: Amendments to Liquefied Natural Gas Facilities, 2026-11-03
- [2026-13805](https://policyrisk.com/federal-register/2026-13805): Pipeline Safety: Repair Criteria for Hazardous Liquid and Gas Transmission Pipelines, 2026-07-08
- [2026-10969](https://policyrisk.com/federal-register/2026-10969): Pipeline Safety: Breakout Tank Inspection Rule, 2026-06-02
- [2026-10782](https://policyrisk.com/federal-register/2026-10782): Pipeline Safety: Class Location Change Requirements; Correction, 2026-05-29
- [2026-08144](https://policyrisk.com/federal-register/2026-08144): Administrative Rulemaking, Guidance, and Enforcement Procedures, 2026-04-27
- [2026-08058](https://policyrisk.com/federal-register/2026-08058): Pipeline Safety: Safety of Gas Transmission Pipelines: MAOP Reconfirmation, Expansion of Assessment Requirements, and Other Related Amendme…, 2026-04-24

## Sources
- [2025-11786 on federalregister.gov](https://www.federalregister.gov/documents/2025/06/26/2025-11786/pipeline-safety-request-for-special-permit)
- [2025-11786 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-06-26/pdf/2025-11786.pdf)

## Related
- [Previous: 2025-11785, Pipeline Safety: Request for Special Permit](https://policyrisk.com/federal-register/2025-11785)
- [Next: 2025-11787, Pipeline Safety: Request for Special Permit](https://policyrisk.com/federal-register/2025-11787)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-11786 (as of 2026-11-05).