# 2025-11829: One Drop Hydro Drips into Rhode Island River Licensing

2025-11829, One Drop Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Licensing, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-06-26, effective The notice was published June 26, 2025; key procedural deadlines include: 60 days from filing (deadline for study requests) and a filing deadline of August 11, 2025 for additional study requests and cooperating agency status; other schedule milestones through January 2026. (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-11829
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-11829
- Title: One Drop Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Licensing
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 27296
- Published: 2025-06-26
- Effective: The notice was published June 26, 2025; key procedural deadlines include: 60 days from filing (deadline for study requests) and a filing deadline of August 11, 2025 for additional study requests and cooperating agency status; other schedule milestones through January 2026.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

One Drop Hydro Drips into Rhode Island River Licensing

## Summary

One Drop Hydro, LLC just applied for a new license to build a small hydroelectric project on the Blackstone River in Rhode Island. This means local communities and environmental groups have until August 11, 2025, to ask for extra studies or get involved before the project moves forward. The process could bring clean energy but also needs careful review to protect the river and surrounding areas.

## Effects PRIA read

- Deadline to Request Extra Studies: benefit, low. If you are a local resident, resource agency, Tribal government, or environmental group, you have until 5:00 p.m. Eastern Time on August 11, 2025 to file a request with the Federal Energy Regulatory Commission asking for additional scientific studies or to request cooperating-agency status for the…
- New Small Hydropower Added to Grid: mixed, low. One Drop Hydro proposes the Elizabeth Webbing Falls project in Providence County, Rhode Island that would operate in run-of-river mode and produce an estimated 3,400 megawatt-hours per year using an existing 0.7 megawatt generator and a new 400-foot transmission line to Rhode Island Energy's distri…
- Required Environmental Measures Proposed: benefit, low. The applicant proposes environmental protections including operating the project in run-of-river mode, releasing a continuous minimum flow of 250 cubic feet per second (or inflow, whichever is less) to the bypassed reach, installing a volitional eel passage ramp at the spillway, installing downstre…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-11829 on federalregister.gov](https://www.federalregister.gov/documents/2025/06/26/2025-11829/one-drop-hydro-llc-notice-of-application-tendered-for-filing-with-the-commission-and-soliciting)
- [2025-11829 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-06-26/pdf/2025-11829.pdf)

## Related
- [Previous: 2025-11828, Federal and State Current Issues Collaborative; Notice Announcing Meeting](https://policyrisk.com/federal-register/2025-11828)
- [Next: 2025-11830, Equitrans, L.P.; Notice of Request for Extension of Time](https://policyrisk.com/federal-register/2025-11830)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-11829 (as of 2026-06-08).