# 2025-12154: Transit Project Guidance Moves Out of an Outdated Appendix

2025-12154, Major Capital Investment Projects, is a Federal Register rule from Transportation Department, Federal Transit Administration published 2025-07-01, effective 2025-07-01; PRIA reads it as touching household money (as of 2026-11-06).

- Canonical: https://policyrisk.com/federal-register/2025-12154
- As of: 2026-11-06
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-12154
- Title: Major Capital Investment Projects
- Type: Rule
- Agencies: Transportation Department; Federal Transit Administration
- Citation: 90 FR 28229
- Published: 2025-07-01
- Effective: 2025-07-01
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: 2132-AB55
- Last updated: 2026-11-06

## In one line

Transit Project Guidance Moves Out of an Outdated Appendix

## Summary

Starting July 1, 2025, the Federal Transit Administration is updating how it handles big transit project rules by removing an old appendix that had outdated info. Now, the latest project evaluation details will live only in the regularly updated policy guide, making things clearer and more current for transit planners and local governments seeking funding. This change helps speed up updates without confusing everyone with old rules.

## Abstract

This rulemaking revises FTA's major capital investment projects regulation to remove Appendix A, which provided outdated descriptions of the measures used for the evaluation of Capital Investment Grant (CIG) projects. This rulemaking also adopts minor conforming changes to reflect the removal of the Appendix.

## Effects PRIA read

- Appendix A removed; guidance is definitive: benefit, low. Starting July 1, 2025, Appendix A is removed from 49 CFR part 611. You must rely on the Capital Investment Grant (CIG) Policy Guidance — not the old Appendix — for the detailed measures used to evaluate CIG projects.
- CIG Policy Guidance updated regularly: benefit, medium. FTA will publish the detailed project evaluation measures in the CIG Policy Guidance, which must be updated at least once every two years and was last updated in December 2024. When the guidance imposes a "binding obligation," FTA follows notice-and-comment procedures so interested parties can comm…
- No change to evaluation outcomes: benefit, low. FTA says removing Appendix A will have no substantive effect on how CIG projects are evaluated or rated. The change is intended to conform the regulation to current practice and avoid confusion from obsolete text.
- Existing projects stay under old rules: benefit, low. Projects with an executed Full Funding Grant Agreement (FFGA) or Pre-Construction Grant Agreement (PCGA), or projects approved into final design or project development, continue under the prior regulations unless the project sponsor asks to be covered by the revised part 611.
- New Starts / Small Starts financial thresholds: mixed, high. A New Starts project is defined as a project with total capital cost of $250,000,000 or more or for which the sponsor requests $75,000,000 or more in New Starts funds. A Small Starts project has total capital cost under $250,000,000 and requests less than $75,000,000.
- Before-and-After study required for New Starts: mixed, medium. During engineering, New Starts project sponsors must submit a plan to collect and analyze "before" and "after" data, including capital costs, operating costs, ridership, and service characteristics. A final report must be prepared within three years of project opening, and satisfactory progress on…
- Rating thresholds to get construction grants: cost, high. To be eligible for construction grants under 49 U.S.C. 5309, New Starts and Small Starts projects must receive a "medium" or better rating on project justification and a "medium" or better rating on local financial commitment before construction grant approval.

## Related documents

- [2026-17904](https://policyrisk.com/federal-register/2026-17904): National Environmental Policy Act Regulations, 2026-09-01
- [2026-08144](https://policyrisk.com/federal-register/2026-08144): Administrative Rulemaking, Guidance, and Enforcement Procedures, 2026-04-27
- [2026-22168](https://policyrisk.com/federal-register/2026-22168): Safety Advisory 26-01 Overhead Catenary System (OCS) and Pantograph Reliability, 2026-10-30
- [2026-21945](https://policyrisk.com/federal-register/2026-21945): Transfer of Federally Assisted Property, 2026-10-28
- [2026-20514](https://policyrisk.com/federal-register/2026-20514): Agency Information Collection Activity Under OMB Review: 49 U.S.C. 5307 Urbanized Area Formula Program, 2026-10-07
- [2026-20515](https://policyrisk.com/federal-register/2026-20515): Agency Information Collection Activity Under OMB Review: 49 U.S.C. 5317 New Freedom Program, 2026-10-07

## Sources
- [2025-12154 on federalregister.gov](https://www.federalregister.gov/documents/2025/07/01/2025-12154/major-capital-investment-projects)
- [2025-12154 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-07-01/pdf/2025-12154.pdf)

## Related
- [Previous: 2025-12153, Administrative Updates to the Railroad Safety Appliance Standards Regulations](https://policyrisk.com/federal-register/2025-12153)
- [Next: 2025-12155, Repealing a Redundant Reporting Requirement](https://policyrisk.com/federal-register/2025-12155)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-12154 (as of 2026-11-06).