# 2025-12367: NRC Lists Routine Nuclear Plant License Changes for Review

2025-12367, Monthly Notice; Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations, is a Federal Register notice from Nuclear Regulatory Commission published 2025-07-08, effective 2025-07-08; PRIA reads it as touching household money (as of 2026-11-10).

- Canonical: https://policyrisk.com/federal-register/2025-12367
- As of: 2026-11-10
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-12367
- Title: Monthly Notice; Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 90 FR 30110
- Published: 2025-07-08
- Effective: 2025-07-08
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-10

## In one line

NRC Lists Routine Nuclear Plant License Changes for Review

## Summary

The Nuclear Regulatory Commission is sharing updates on changes to nuclear plant licenses that don’t pose big safety risks. These updates affect plant operators and the public, with a chance to comment or request hearings by early August and September 2025. No major cost or safety issues are expected, so plants can keep running smoothly while these changes happen.

## Abstract

Pursuant to section 189a.(2) of the Atomic Energy Act of 1954, as amended (the Act), the U.S. Nuclear Regulatory Commission (NRC) is publishing this regular monthly notice. The Act requires the Commission to publish notice of any amendments issued, or proposed to be issued, and grants the Commission the authority to issue and make immediately effective any amendment to an operating license or combined license, as applicable, upon a determination by the Commission that such amendment involves no significant hazards consideration (NSHC), notwithstanding the pendency before the Commission of a request for a hearing from any person.

## Effects PRIA read

- Public comment and hearing deadlines: benefit, low. You can submit public comments on the NRC's listed license amendments by August 7, 2025, and you can request a hearing or file a petition to intervene by September 8, 2025. The notice covers amendment actions proposed or issued from May 23, 2025, to June 18, 2025.
- Amendments can take effect immediately: benefit, medium. The NRC may issue a license amendment before the normal 60-day notice period if it determines the change involves no significant hazards consideration (NSHC). The Commission may also issue an amendment before the 30-day comment period ends if not acting would cause derating or shutdown of the facil…
- Oyster Creek decommissioning plan added: benefit, medium. Holtec's proposed amendment would incorporate the Oyster Creek Nuclear Generating Station License Termination Plan (LTP) into the license; the LTP outlines how the site will be decommissioned and how residual radioactivity will be addressed to meet criteria for unrestricted use, and upon approval t…
- Ginna NaOH system completion time extended: cost, low. R.E. Ginna Nuclear Power Plant's proposed amendment would extend the Required Action B completion time to restore the Sodium Hydroxide (NaOH) system from 72 hours to 14 days for Technical Specification 3.6.6.
- Seabrook emergency action level change: benefit, low. NextEra's Seabrook Station proposed amendment would change the Emergency Action Levels for Initiating Condition HU4 in procedure ER 1.1, "Classification of Emergencies," due to the implementation of a new fire detection system inside the Seabrook Containment Building.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2025-12367 on federalregister.gov](https://www.federalregister.gov/documents/2025/07/08/2025-12367/monthly-notice-applications-and-amendments-to-facility-operating-licenses-and-combined-licenses)
- [2025-12367 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-07-08/pdf/2025-12367.pdf)

## Related
- [Previous: 2025-12624, Sunshine Act Meetings](https://policyrisk.com/federal-register/2025-12624)
- [Next: 2025-12606, Notice of Intent To Extend and Revise a Previously Approved Information Collect…](https://policyrisk.com/federal-register/2025-12606)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-12367 (as of 2026-11-10).