# 2025-13126: Pipeline Project Seeks Your Eco-Opinions in Utah Wilderness

2025-13126, Northwest Pipeline, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Wild Trail Project, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-07-14, effective Comments must be received in Washington, DC on or before 5:00 p.m. Eastern Time on August 8, 2025. (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-13126
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-13126
- Title: Northwest Pipeline, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Wild Trail Project
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 31197
- Published: 2025-07-14
- Effective: Comments must be received in Washington, DC on or before 5:00 p.m. Eastern Time on August 8, 2025.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Pipeline Project Seeks Your Eco-Opinions in Utah Wilderness

## Summary

Northwest Pipeline wants to build the Wild Trail Project in Utah, and the government is asking people to share their thoughts on how it might affect the environment. If you live nearby or care about nature, now’s the time to speak up before August 8, 2025. Your input will help decide if the project moves forward and how it might change the area.

## Effects PRIA read

- Public comment window open until August 8, 2025: benefit, low. You can submit formal comments about the Wild Trail Project to FERC by 5:00 p.m. Eastern Time on August 8, 2025. Comments may be filed electronically via eComment or eFiling on www.ferc.gov, or by mail referencing Docket No. CP25-497-000; public input will be used to shape the environmental review.
- Permanent land converted for compressor station use: cost, low. Construction would require about 20.25 acres of land near the Clay Basin Meter Station, including 15.86 acres on Bureau of Land Management land and 4.39 acres of temporary workspace in Ashley National Forest. After construction and restoration, about 6.77 acres would be permanently converted to nat…
- Multiple environmental resource areas will be evaluated: benefit, low. FERC staff will evaluate the project's effects on geology and soils; water resources and wetlands; vegetation and wildlife; threatened and endangered species; cultural resources; land use; socioeconomics; air quality and noise; and reliability and safety. The environmental document (EA or EIS) will…
- BLM and Forest Service as cooperating agencies: cost, low. The Bureau of Land Management (BLM) and U.S. Forest Service have agreed to be cooperating agencies on the environmental review and will participate in preparation of the EA or EIS. The BLM states it will use the EA to consider issuing a right-of-way for the proposed Wild Trail Compressor Facility u…
- Historic properties consultation begins under Section 106: benefit, low. FERC is initiating consultation under Section 106 of the National Historic Preservation Act with the Utah State Historic Preservation Office, Tribes, other agencies, and the public to identify and address potential effects on historic properties. The environmental document will summarize the status…
- Landowners were sent FERC eminent domain fact sheet: benefit, low. Northwest provided landowners with FERC's fact sheet titled "An Interstate Natural Gas Facility On My Land? What Do I Need To Know?" which covers common questions including the use of eminent domain and how to participate in the proceeding. The fact sheet and other landowner materials are available…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-13126 on federalregister.gov](https://www.federalregister.gov/documents/2025/07/14/2025-13126/northwest-pipeline-llc-notice-of-scoping-period-requesting-comments-on-environmental-issues-for-the)
- [2025-13126 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-07-14/pdf/2025-13126.pdf)

## Related
- [Previous: 2025-13125, Agency Information Collection Activities Under OMB Review](https://policyrisk.com/federal-register/2025-13125)
- [Next: 2025-13139, Sunshine Act Meetings](https://policyrisk.com/federal-register/2025-13139)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-13126 (as of 2026-06-08).