# 2025-13174: TVA's Clinch River Nuclear Project Enters Federal Review

2025-13174, Tennessee Valley Authority; Clinch River Nuclear Site, Unit 1; Construction Permit Application, is a Federal Register notice from Nuclear Regulatory Commission published 2025-07-15, effective 2025-07-15 (as of 2026-11-12).

- Canonical: https://policyrisk.com/federal-register/2025-13174
- As of: 2026-11-12
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-13174
- Title: Tennessee Valley Authority; Clinch River Nuclear Site, Unit 1; Construction Permit Application
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 90 FR 31709
- Published: 2025-07-15
- Effective: 2025-07-15
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-11-12

## In one line

TVA's Clinch River Nuclear Project Enters Federal Review

## Summary

The Tennessee Valley Authority (TVA) wants to build a new nuclear reactor at the Clinch River site in Tennessee, and the Nuclear Regulatory Commission (NRC) just accepted their construction permit application for review. People have until September 15, 2025, to ask for a hearing or get involved, and the NRC is carefully checking the technical details now. If approved, TVA can start building, which could bring jobs and energy to the area!

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) has accepted for review and docketed an application from Tennessee Valley Authority (TVA) for a construction permit for the Clinch River Nuclear Site, Unit 1 reactor to be built in Roane County, Tennessee. In addition, the NRC is providing notice that an uncontested hearing will be held on the TVA construction permit application at a time and place to be set in the future by the presiding officer for the uncontested hearing. This notice also provides the public an opportunity to request a hearing and petition for leave to intervene (i.e., contested hearing) with respect to that application. The NRC staff is currently conducting a detailed technical review of the construction permit application. If the NRC issues a construction permit, the applicant, TVA, would be authorized to construct its proposed reactor in accordance with the provisions of the construction permit. Because the application contains Sensitive Unclassified Non-Safeguards Information (SUNSI), this notice includes an order that imposes procedures to obtain access to SUNSI for contention preparation.

## Effects PRIA read

- You can ask for a hearing by Sept 15, 2025: benefit, low. If you think your interests may be affected by TVA’s Clinch River Unit 1 construction-permit application, you can file a request for a hearing and petition to intervene. Petitions must be filed no later than September 15, 2025 (60 days from the Federal Register notice), and must follow the Commissi…
- How to request access to SUNSI (by July 25, 2025): benefit, medium. If you need access to Sensitive Unclassified Non-Safeguards Information (SUNSI) to prepare a contention, you must request access within 10 days after the Federal Register notice—i.e., by July 25, 2025. The request must give your name and address, describe your particularized interest, and explain w…
- E-Filing rules you must follow to participate: cost, low. If you file documents in the NRC adjudicatory proceeding you generally must use the NRC E-Filing system. At least 10 days before the filing deadline you should contact the Office of the Secretary to request a digital ID certificate and notify them you will submit a petition; electronic filings must…

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2025-13174 on federalregister.gov](https://www.federalregister.gov/documents/2025/07/15/2025-13174/tennessee-valley-authority-clinch-river-nuclear-site-unit-1-construction-permit-application)
- [2025-13174 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-07-15/pdf/2025-13174.pdf)

## Related
- [Previous: 2025-13171, Agency Information Collection Activities; Submission to the Office of Managemen…](https://policyrisk.com/federal-register/2025-13171)
- [Next: 2025-13176, Agency Information Collection Activities; Submission for OMB Review; Comment Re…](https://policyrisk.com/federal-register/2025-13176)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-13174 (as of 2026-11-12).