# 2025-13327: Minnesota Air Rules Get a Routine Federal Alignment Check

2025-13327, Air Plan Approval; Minnesota; Exempt Source SIP Revision, is a Federal Register proposed rule from Environmental Protection Agency published 2025-07-16, effective Comments must be received on or before August 15, 2025.; PRIA reads it as touching household money (as of 2026-11-13).

- Canonical: https://policyrisk.com/federal-register/2025-13327
- As of: 2026-11-13
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-13327
- Title: Air Plan Approval; Minnesota; Exempt Source SIP Revision
- Type: Proposed Rule
- Agencies: Environmental Protection Agency
- Citation: 90 FR 31918
- Published: 2025-07-16
- Effective: Comments must be received on or before August 15, 2025.
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-13

## In one line

Minnesota Air Rules Get a Routine Federal Alignment Check

## Summary

The EPA wants to approve updates to Minnesota’s air quality rules to match recent state changes made since July 2020. This means businesses and residents in Minnesota will follow clearer, consistent air pollution rules at both state and federal levels. You’ve got until August 15, 2025, to share your thoughts—no extra costs or deadlines beyond that!

## Abstract

The Environmental Protection Agency (EPA) is proposing to approve a revision to the Minnesota State Implementation Plan (SIP) which updates Minnesota's air program rules. The Minnesota Pollution Control Agency (MPCA) submitted the request to EPA on October 1, 2021. The revision to Minnesota's air quality rules will reflect changes that have occurred to the State air quality rules since July 2020. EPA is proposing to approve MPCA's submittal, which will result in consistent requirements of rules at both the State and Federal level.

## Effects PRIA read

- New permit-by-rule exemptions for auto‑body and coating shops: benefit, medium. Minnesota added permit-by-rule exemptions for auto-body refinishing and for other coating facilities so they may operate without an air emissions permit if they meet written limits and requirements. Each of these two categories is limited to 2,000 gallons of coating and cleaning materials per calen…
- New woodworking exemption with control options: benefit, medium. Minnesota added a conditionally exempt category for woodworking facilities that lets eligible woodworking shops operate without a permit if they meet eligibility rules and one of five control options that keep particulate emissions below permitting thresholds. The rule lists operational, control, r…
- New "insignificant facility" exemption category: benefit, medium. Minnesota created a new exempt category for facilities that have only insignificant and conditionally insignificant activities; such an 'insignificant facility' can operate without a permit if the number of emission units and calculated potential emissions do not exceed listed permitting thresholds…
- Higher thresholds for conditionally insignificant material use: benefit, medium. Minnesota raised eligibility thresholds for conditionally insignificant material use: volatile organic compound (VOC) emission thresholds increased from less than 2,000 pounds to less than 10,000 pounds, and VOC-containing material usage limits rose from less than 200 gallons to less than 1,000 gal…
- Public notice moves to electronic posting; hearing petition changes: benefit, low. Minnesota revised permit public notice rules to remove the requirement for newspaper or State Register notice and instead require electronic posting of the public notice (including the draft permit and a statement about any pollution prevention progress report) on MPCA's public notice website for t…
- Clarified permit renewal timing (18‑month rule): benefit, low. Minnesota clarified that a owner or operator will not be required to submit a renewal application sooner than 18 months prior to permit expiration for a Federal part 70 permit. This aligns State and Federal permitting timing.
- Owners/operators must reassess permit need after emissions changes: cost, low. Minnesota added a requirement that if a change at a facility affects the amount or type of pollutants emitted, the owner or operator must determine whether a permit is needed and follow permitting requirements at Minn. R. 7007.0400, subpart 4. This strengthens current SIP requirements.

## Related documents

- [2026-22082](https://policyrisk.com/federal-register/2026-22082): Additional Reconsideration Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sour…, 2026-10-29
- [2026-21155](https://policyrisk.com/federal-register/2026-21155): Renewable Fuel Standard (RFS) Program: Reallocation of Additional 2025 Small Refinery Exemptions, 2026-10-16
- [2026-20849](https://policyrisk.com/federal-register/2026-20849): Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy, 2026-10-13
- [2026-19072](https://policyrisk.com/federal-register/2026-19072): Rescission of the Greenhouse Gas Findings for Fossil Fuel-Fired Power Plants and Repeal of Regulations for Power Plant Greenhouse Gas Emiss…, 2026-09-17
- [2026-19071](https://policyrisk.com/federal-register/2026-19071): Partial Repeal of the Carbon Pollution Standards for Fossil Fuel-Fired Electric Generating Units, 2026-09-17
- [2026-18317](https://policyrisk.com/federal-register/2026-18317): Updated Definition of “Waters of the United States”, 2026-09-09

## Sources
- [2025-13327 on federalregister.gov](https://www.federalregister.gov/documents/2025/07/16/2025-13327/air-plan-approval-minnesota-exempt-source-sip-revision)
- [2025-13327 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-07-16/pdf/2025-13327.pdf)

## Related
- [Previous: 2025-13325, Air Plan Approval; Indiana; Regional Haze Plan for the Second Implementation Pe…](https://policyrisk.com/federal-register/2025-13325)
- [Next: 2025-13335, Air Plan Approval; Guam; Base Year Emissions Inventory for the 2010 1-Hour Sulf…](https://policyrisk.com/federal-register/2025-13335)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-13327 (as of 2026-11-13).