# 2025-17407: Gas Giants Plan Southern Pipeline Push: Feds Call for Comments

2025-17407, Tennessee Gas Pipeline Company, LLC, Southern Natural Gas Company, LLC, Elba Express Company, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Proposed Mississippi Crossing Project and South System Expansion 4 Project Request for Comments on Environmental Issues, and Schedule for Environmental Review, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-09-10, effective 2026-06-26 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-17407
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-17407
- Title: Tennessee Gas Pipeline Company, LLC, Southern Natural Gas Company, LLC, Elba Express Company, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Proposed Mississippi Crossing Project and South System Expansion 4 Project Request for Comments on Environmental Issues, and Schedule for Environmental Review
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 43593
- Published: 2025-09-10
- Effective: 2026-06-26
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Gas Giants Plan Southern Pipeline Push: Feds Call for Comments

## Summary

Tennessee Gas Pipeline, Southern Natural Gas, and Elba Express are planning big projects to build and upgrade gas pipelines across parts of Mississippi, Alabama, and Georgia. The government is checking how these projects might affect the environment and wants your thoughts before moving forward. This review will help decide if the projects are safe and necessary, with updates coming soon on timing and costs.

## Effects PRIA read

- Landowners face eminent domain risk: cost, high. If you are a landowner in the project area, the pipeline companies may contact you to negotiate an easement but you are not required to agree. If FERC approves the Projects, the Natural Gas Act gives the company the right to initiate condemnation (eminent domain) proceedings in court and a judge wo…
- Wetlands and waterbody impacts: cost, medium. The MSX Project would impact about 146.4 acres of wetlands during construction and about 73.7 acres during operation and traverse roughly 1,000 waterbodies; the SSE4 Project would impact about 223.8 acres of wetlands during construction and about 48.6 acres during operation and also traverse over 1…
- Large construction footprint and land maintenance: cost, medium. Construction for the MSX Project would disturb about 2,900 acres and the SSE4 Project about 6,865 acres; afterward TGP would maintain about 1,460 acres for MSX and SNG/EEC about 1,465 acres for SSE4, with the rest restored. About 28% of the MSX route and about 92% of the SSE4 route parallel existin…
- Regional pipeline capacity increases: benefit, medium. The MSX Project is designed to add about 2.1 billion cubic feet per day (Bcf/d) of firm transportation capacity to the southeast, and the SSE4 Project would add about 1.323 Bcf/d of firm capacity to the southeast. The companies say these capacities are meant to meet growing residential, commercial,…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-17407 on federalregister.gov](https://www.federalregister.gov/documents/2025/09/10/2025-17407/tennessee-gas-pipeline-company-llc-southern-natural-gas-company-llc-elba-express-company-llc-notice)
- [2025-17407 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-09-10/pdf/2025-17407.pdf)

## Related
- [Previous: 2025-17406, Gulf South Pipeline Company; Notice of Availability of the Environmental Assess…](https://policyrisk.com/federal-register/2025-17406)
- [Next: 2025-17408, Eastern Gas Transmission and Storage, Inc.; Notice of Scoping Period Requesting…](https://policyrisk.com/federal-register/2025-17408)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-17407 (as of 2026-06-08).