2025-17518, Maryland: Final Approval of State Underground Storage Tank Program Revisions, Codification, and Incorporation by Reference, is a Federal Register proposed rule from Environmental Protection Agency published 2025-09-11, effective Effective 60 days from the date of publication in the Federal Register. (as of 2026-06-11).

- Canonical: https://policyrisk.com/federal-register/2025-17518
- As of: 2026-06-11
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-17518
- Title: Maryland: Final Approval of State Underground Storage Tank Program Revisions, Codification, and Incorporation by Reference
- Type: Proposed Rule
- Agencies: Environmental Protection Agency
- Citation: 90 FR 43987
- Published: 2025-09-11
- Effective: Effective 60 days from the date of publication in the Federal Register.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-11

## In one line

EPA Approves Maryland's Safer Underground Tank Standards

## Summary

Maryland’s updated rules for underground storage tanks just got the EPA’s thumbs-up! This means tank owners and operators in Maryland must follow the new safety and inspection standards starting 60 days after this announcement. The changes help protect the environment and keep tanks safer without adding extra costs right now.

## Abstract

Pursuant to the Solid Waste Disposal Act of 1965, as amended (commonly known as the Resource Conservation and Recovery Act (RCRA)), the Environmental Protection Agency (EPA) is proposing to approve revisions to the State of Maryland's Underground Storage Tank (UST) program submitted by Maryland (Maryland or State). This action is based on EPA's determination that these revisions satisfy all the requirements needed for program approval. This action also proposes to codify EPA's approval of Maryland's state program and to incorporate by reference (IBR) those provisions of Maryland's regulations and statutes that EPA has determined meet the requirements for approval. The provisions will be subject to EPA's inspection and enforcement authorities under sections 9005 and 9006 of RCRA Subtitle I and other applicable statutory and regulatory provisions. In the "Rules and Regulations" section of this issue of the Federal Register, EPA is approving this action by a direct final rule. If no significant negative comment is received, EPA will not take further action on this proposed rulemaking, and the direct final rule will be effective 60 days from the date of publication in this Federal Register. If you want to comment on EPA's proposed approval of Maryland's revisions to its state UST program, you must do so at this time.

## Effects PRIA read

- Maryland USTs: New safety rules in 60 days: benefit, low. If you own or operate an underground storage tank in Maryland, you must follow Maryland's updated safety and inspection standards starting 60 days after the rule's publication in the Federal Register. The EPA approved these revisions and the rule says the changes help protect the environment and ke…
- EPA inspection and enforcement now applies: benefit, low. Maryland's approved underground storage tank provisions will be subject to EPA inspection and enforcement authorities under sections 9005 and 9006 of the Resource Conservation and Recovery Act (RCRA) Subtitle I. That means EPA can inspect and enforce those Maryland UST rules once the approval is fi…

## Related documents

- [2026-22082](https://policyrisk.com/federal-register/2026-22082): Additional Reconsideration Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sour…, 2026-10-29
- [2026-21155](https://policyrisk.com/federal-register/2026-21155): Renewable Fuel Standard (RFS) Program: Reallocation of Additional 2025 Small Refinery Exemptions, 2026-10-16
- [2026-20849](https://policyrisk.com/federal-register/2026-20849): Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy, 2026-10-13
- [2026-19071](https://policyrisk.com/federal-register/2026-19071): Partial Repeal of the Carbon Pollution Standards for Fossil Fuel-Fired Electric Generating Units, 2026-09-17
- [2026-19072](https://policyrisk.com/federal-register/2026-19072): Rescission of the Greenhouse Gas Findings for Fossil Fuel-Fired Power Plants and Repeal of Regulations for Power Plant Greenhouse Gas Emiss…, 2026-09-17
- [2026-18317](https://policyrisk.com/federal-register/2026-18317): Updated Definition of “Waters of the United States”, 2026-09-09

## Sources
- [2025-17518 on federalregister.gov](https://www.federalregister.gov/documents/2025/09/11/2025-17518/maryland-final-approval-of-state-underground-storage-tank-program-revisions-codification-and)
- [2025-17518 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-09-11/pdf/2025-17518.pdf)

## Related
- [Previous: 2025-17505, Proposed Deletion From the National Priorities List](https://policyrisk.com/federal-register/2025-17505)
- [Next: 2025-17520, Minnesota: Final Approval of State Underground Storage Tank Program Revisions,…](https://policyrisk.com/federal-register/2025-17520)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-17518 (as of 2026-06-11).