# 2025-19989: Oklahoma's Air Rules Get EPA Nod for Cleaner Permits

2025-19989, Air Plan Approval; Oklahoma; Updates to the State Implementation Plan for New Source Review Permitting and General SIP Provisions, is a Federal Register proposed rule from Environmental Protection Agency published 2025-11-17, effective Written comments must be received on or before December 17, 2025. (as of 2026-06-11).

- Canonical: https://policyrisk.com/federal-register/2025-19989
- As of: 2026-06-11
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-19989
- Title: Air Plan Approval; Oklahoma; Updates to the State Implementation Plan for New Source Review Permitting and General SIP Provisions
- Type: Proposed Rule
- Agencies: Environmental Protection Agency
- Citation: 90 FR 51247
- Published: 2025-11-17
- Effective: Written comments must be received on or before December 17, 2025.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-11

## In one line

Oklahoma's Air Rules Get EPA Nod for Cleaner Permits

## Summary

Oklahoma is updating its air pollution rules to make sure new factories and projects follow cleaner standards. These changes affect businesses applying for air permits and help keep the air safer for everyone. You’ve got until December 17, 2025, to share your thoughts before the updates go live—no extra costs are expected, just clearer rules!

## Abstract

Pursuant to the Federal Clean Air Act (CAA or the Act), the Environmental Protection Agency (EPA) is proposing to approve identified portions of revisions to the Oklahoma State Implementation Plan (SIP) submitted by the State of Oklahoma designee between 2002 and 2025 to update the Oklahoma New Source Review (NSR) permit program and make general updates to the Oklahoma SIP.

## Effects PRIA read

- New Enhanced NSR Streamlining Pathway: benefit, medium. Oklahoma added an "enhanced NSR" pathway that lets sources with existing part 70 operating permits incorporate NSR permit terms into their operating permit by administrative amendment. The enhanced pathway is limited to sources with existing part 70 permits and keeps EPA review (45 days) and a 30-d…
- 10 TPY Minor NSR Permit Threshold: cost, medium. Oklahoma added a 10 tons per year (TPY) threshold for changes at sources with existing part 70 permits: any physical change that would increase potential to emit by more than 10 TPY of any regulated pollutant now requires a minor NSR construction permit. Projects below 10 TPY are exempt from that c…
- Start Construction Before Permit Issued: mixed, medium. Oklahoma added provisions allowing an applicant at a Subchapter 8 major source to begin construction after submitting an administratively complete minor NSR application, but not to operate the unit. The rule says construction is at the applicant's risk and expense, the DEQ can deny the permit, and…
- More Public Notice Posted Online: benefit, low. Oklahoma requires the DEQ to post draft Tier II and Tier III individual construction permits on its website and provide a 30-day opportunity for public comment (in addition to newspaper notice). The DEQ must also post Tier I individual construction-permit opportunities for 30 days on the agency web…
- 50% 'Reasonable Possibility' Recordkeeping Rule: cost, low. Oklahoma adopted 'reasonable possibility' criteria for projects using the actual-to-projected-actual test: pre- and post-change recordkeeping and reporting apply when projected emissions are at least 50% of federal significance levels. Oklahoma also requires pre-change recordkeeping for all project…
- EPA Proposal: Approve Oklahoma Minor NSR Program: mixed, medium. EPA proposes to find that Oklahoma's OAC 252:4 and OAC 252:100, Subchapter 8 satisfy federal minor NSR requirements (40 CFR 51.160-51.164), making Subchapter 8 an approvable minor NSR program and removing older Regulation 1.4.1/1.4.2 provisions from the SIP.

## Related documents

- [2026-22082](https://policyrisk.com/federal-register/2026-22082): Additional Reconsideration Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sour…, 2026-10-29
- [2026-21155](https://policyrisk.com/federal-register/2026-21155): Renewable Fuel Standard (RFS) Program: Reallocation of Additional 2025 Small Refinery Exemptions, 2026-10-16
- [2026-20849](https://policyrisk.com/federal-register/2026-20849): Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy, 2026-10-13
- [2026-19071](https://policyrisk.com/federal-register/2026-19071): Partial Repeal of the Carbon Pollution Standards for Fossil Fuel-Fired Electric Generating Units, 2026-09-17
- [2026-19072](https://policyrisk.com/federal-register/2026-19072): Rescission of the Greenhouse Gas Findings for Fossil Fuel-Fired Power Plants and Repeal of Regulations for Power Plant Greenhouse Gas Emiss…, 2026-09-17
- [2026-18317](https://policyrisk.com/federal-register/2026-18317): Updated Definition of “Waters of the United States”, 2026-09-09

## Sources
- [2025-19989 on federalregister.gov](https://www.federalregister.gov/documents/2025/11/17/2025-19989/air-plan-approval-oklahoma-updates-to-the-state-implementation-plan-for-new-source-review-permitting)
- [2025-19989 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-11-17/pdf/2025-19989.pdf)

## Related
- [Previous: 2025-19927, Proposal of Special Measure Regarding Transactions Involving Ten Mexican Gambli…](https://policyrisk.com/federal-register/2025-19927)
- [Next: 2025-19992, Approval of Source-Specific Air Quality Implementation Plan; New York; Calpine…](https://policyrisk.com/federal-register/2025-19992)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-19989 (as of 2026-06-11).