# 2025-20188: Pipeline Gets a Boost: 194,400 Dekatherms and Counting

2025-20188, Rockies Express Pipeline LLC; Notice of Amendment to Application and Establishing Intervention Deadline, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-11-18, effective Intervention Deadline: 5:00 p.m. Eastern Time on December 4, 2025. Rockies Express filed the amendment on October 31, 2025; Federal Register notice dated November 18, 2025. (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-20188
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-20188
- Title: Rockies Express Pipeline LLC; Notice of Amendment to Application and Establishing Intervention Deadline
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 51740
- Published: 2025-11-18
- Effective: Intervention Deadline: 5:00 p.m. Eastern Time on December 4, 2025. Rockies Express filed the amendment on October 31, 2025; Federal Register notice dated November 18, 2025.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Pipeline Gets a Boost: 194,400 Dekatherms and Counting

## Summary

Rockies Express Pipeline is boosting its Decatur Lateral Project’s gas capacity from 181,000 to 194,400 dekatherms per day, thanks to some smart tweaks. They’re also making small changes to the project’s land use, adding about 2.2 acres, but no new facilities. If you want to speak up or get involved, you better act before the set deadline!

## Effects PRIA read

- Project capacity increased 13,000 Dth/d: benefit, medium. Rockies Express amended the Decatur Lateral Project to raise capacity from 181,000 dekatherms per day (Dth/d) to 194,400 Dth/d, an increase of approximately 13,000 Dth/d. The notice states that the new 13,000 Dth/d is fully subscribed by a Project shipper.
- Project footprint grows by 2.2 acres: cost, low. The amendment proposes three scope modifications and one land-ownership change that increase the overall Project footprint by approximately 2.2 acres. The notice also states there are no changes to the proposed facilities.
- Public intervention deadline set: benefit, low. Anyone may file comments, protests, or a motion to intervene in the proceeding, and there is no fee to do so. The deadline to file a motion to intervene is 5:00 p.m. Eastern Time on December 4, 2025.
- Environmental review timing and 90-day rule: mixed, medium. The Commission staff will, within 90 days of this Notice, either complete its environmental review and place it in the public record or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule is issued, federal and state agencies will be notified of timing and must complete all…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-20188 on federalregister.gov](https://www.federalregister.gov/documents/2025/11/18/2025-20188/rockies-express-pipeline-llc-notice-of-amendment-to-application-and-establishing-intervention)
- [2025-20188 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-11-18/pdf/2025-20188.pdf)

## Related
- [Previous: 2025-20187, Texas Gas Transmission, LLC; Notice of Application and Establishing Interventio…](https://policyrisk.com/federal-register/2025-20187)
- [Next: 2025-20189, Combined Notice of Filings](https://policyrisk.com/federal-register/2025-20189)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-20188 (as of 2026-06-08).