# 2025-20898: Authorizations for Certain Activities at Liquefied Natural Gas Plants

2025-20898, Authorizations for Certain Activities at Liquefied Natural Gas Plants, is a Federal Register proposed rule from Energy Department, Federal Energy Regulatory Commission published 2025-11-25, effective Comments are due January 26, 2026.; PRIA reads it as touching household money (as of 2026-06-11).

- Canonical: https://policyrisk.com/federal-register/2025-20898
- As of: 2026-06-11
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-20898
- Title: Authorizations for Certain Activities at Liquefied Natural Gas Plants
- Type: Proposed Rule
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 53251
- Published: 2025-11-25
- Effective: Comments are due January 26, 2026.
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-06-11

## Summary

The Federal Energy Regulatory Commission wants to make it easier and faster for liquefied natural gas (LNG) plants to get approval for certain activities by possibly changing the rules. This could mean fewer paperwork hurdles and quicker green lights for LNG companies, saving time and money. If you’re involved with LNG plants, you have until January 26, 2026, to share your thoughts on these potential changes.

## Abstract

The Federal Energy Regulatory Commission (Commission) seeks information and stakeholder perspectives to help the Commission explore whether, and if so how, to revise our Part 153, 157, and 380 regulations to establish procedures for authorizing activities at liquefied natural gas plants without case-specific authorization orders under sections 3 and 7 of the Natural Gas Act.

## Effects PRIA read

- Possible Blanket Authorizations for LNG: benefit, medium. If you operate an LNG plant, the Federal Energy Regulatory Commission is asking whether it should revise Parts 153, 157, and 380 to allow certain construction, expansion, operation, or modification activities at LNG plants to be authorized without case-specific orders under sections 3 or 7 of the N…
- Considering Tiered Automatic vs Prior Notice System: mixed, medium. The Commission is asking whether to adopt a two-tiered approach like its pipeline blanket program where some LNG activities would be automatically authorized and others would require prior notice; it asks whether to use the same procedures, including issuance of a notice within 10 days of filing an…
- Current Case-by-Case Process Slows Projects: cost, medium. The Commission states that the existing case-by-case review for replacements, modifications, and expansions at operating LNG terminals can be administratively inefficient, may slow needed projects, and create regulatory uncertainty—especially as more LNG facilities operate and some have been in ser…
- Safety, Coordination, and Preconstruction Conditions: mixed, medium. The Commission asks how applicants would show they consulted other federal permitting agencies and met safety and security requirements (for example, PHMSA siting rules, a USCG Waterways Safety Assessment and Letter of Recommendation, Department of War concurrence, state and local safety considerat…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-20898 on federalregister.gov](https://www.federalregister.gov/documents/2025/11/25/2025-20898/authorizations-for-certain-activities-at-liquefied-natural-gas-plants)
- [2025-20898 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-11-25/pdf/2025-20898.pdf)

## Related
- [Previous: 2025-20897, Safe Harbor Policy for Data Providers to Price Index Developers](https://policyrisk.com/federal-register/2025-20897)
- [Next: 2025-20900, Supplemental Review of the Oil Pipeline Index Level](https://policyrisk.com/federal-register/2025-20900)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-20898 (as of 2026-06-11).