2025-21052, Fall River Rural Electric Cooperative, Inc.; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2025-11-25, effective 2025-11-25 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2025-21052
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-21052
- Title: Fall River Rural Electric Cooperative, Inc.; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 90 FR 53298
- Published: 2025-11-25
- Effective: 2025-11-25
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## Summary

Fall River Rural Electric Cooperative wants a new license to run the Felt Hydroelectric Project on the Teton River in Idaho. The government is now reviewing the environmental impact and asking the public to share their thoughts by December 1, 2025. This process could affect local land and energy use, so your input matters before final decisions and possible changes happen.

## Effects PRIA read

- Minimum River Flows Required by Project: benefit, medium. The Felt Hydroelectric Project is required to discharge a minimum flow of 20 cubic feet per second (cfs) from July 1 to March 14 and 50 cfs from March 15 to June 30 into the bypassed river reaches. The project normally operates run-of-river and has a maximum hydraulic capacity of 900 cfs when all t…
- Plans to Improve Recreation Access: benefit, low. Fall River proposes to improve the portage trail and the recreation access trail at the Felt Hydroelectric Project and maintains a parking area, restroom, signage, and a boating take-out. These changes are part of the applicant's proposals included in the license application.
- Safety Warning Sirens to Be Installed: benefit, low. The applicant proposes to install a warning siren at both powerhouses to alert visitors of sudden flow changes caused by sudden tripping of the project. This measure is intended to warn visitors of sudden increases or changes in flows.
- Conservation Plan for Yellowstone Cutthroat Trout: benefit, medium. Fall River proposes to implement a Yellowstone cutthroat trout conservation plan as part of its license application for the Felt Hydroelectric Project. The proposal is included in the materials being considered during the environmental analysis.
- Proposed Reduction of Project Boundary Acreage: mixed, low. Fall River proposes to remove 30.14 acres of land from the current Felt Project boundary, which occupies federal land administered by the Bureau of Land Management. The proposal is part of the application materials being evaluated during environmental analysis.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2025-21052 on federalregister.gov](https://www.federalregister.gov/documents/2025/11/25/2025-21052/fall-river-rural-electric-cooperative-inc-notice-of-application-ready-for-environmental-analysis-and)
- [2025-21052 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-11-25/pdf/2025-21052.pdf)

## Related
- [Previous: 2025-21051, Forestport Hydro, LLC; Notice of Application Ready for Environmental Analysis a…](https://policyrisk.com/federal-register/2025-21051)
- [Next: 2025-21053, Center for Scientific Review; Notice of Closed Meetings](https://policyrisk.com/federal-register/2025-21053)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-21052 (as of 2026-06-08).