# 2025-21597: EPA Grants Coal Plants Three More Years for Ash Pond Closures

2025-21597, Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Extension of an Alternative Closure Requirement Deadline, is a Federal Register proposed rule from Environmental Protection Agency published 2025-11-28, effective Proposes to extend the compliance deadline for closure of unlined CCR surface impoundments larger than 40 acres from October 17, 2028 to October 17, 2031 (proposed rule; comment deadline January 7, 2026).; PRIA reads it as touching household money (as of 2026-06-11).

- Canonical: https://policyrisk.com/federal-register/2025-21597
- As of: 2026-06-11
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2025-21597
- Title: Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Extension of an Alternative Closure Requirement Deadline
- Type: Proposed Rule
- Agencies: Environmental Protection Agency
- Citation: 90 FR 54611
- Published: 2025-11-28
- Effective: Proposes to extend the compliance deadline for closure of unlined CCR surface impoundments larger than 40 acres from October 17, 2028 to October 17, 2031 (proposed rule; comment deadline January 7, 2026).
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: 2050-AH42
- Last updated: 2026-06-11

## In one line

EPA Grants Coal Plants Three More Years for Ash Pond Closures

## Summary

The EPA is giving coal power plants three more years to close big, unlined coal ash ponds, moving the deadline from 2028 to 2031. This helps some plants keep running longer to keep the lights on without rushing costly closures. If you own or run these sites, this extra time means more flexibility and a smoother transition.

## Abstract

The Environmental Protection Agency (EPA or the Agency) is proposing to extend, by three years, one compliance deadline applicable to certain coal combustion residuals (CCR) surface impoundments operating pursuant to the alternative closure requirements. Specifically, EPA is extending the deadline for owners and operators to complete closure of their unlined CCR surface impoundments larger than 40 acres from October 17, 2028, to October 17, 2031. This deadline extension will promote electric grid reliability by allowing a subset of coal-fired power producers to continue to operate beyond their currently scheduled retirement date.

## Effects PRIA read

- Three‑Year Extension for Large Coal‑Ash Ponds: benefit, medium. The EPA proposes to move the deadline to complete closure of unlined coal combustion residual (CCR) surface impoundments larger than 40 acres from October 17, 2028 to October 17, 2031. This change applies only to owners/operators with extension demonstrations under 40 CFR 257.103(f)(2) and would al…
- Estimated Cost Savings and Preserved Capacity: benefit, medium. EPA's Regulatory Impact Analysis estimates annualized cost savings from this proposed extension of about $7–12 million per year using a 3% discount rate, or about $17–27 million per year using a 7% discount rate. EPA also estimates the extension could preserve roughly 3,200 MW in MISO (about 10% of…
- Environmental Monitoring and Risk Mitigation Stay In Place: mixed, medium. Facilities that operate under the extended deadline would remain subject to existing groundwater monitoring, assessment, and corrective action requirements (40 CFR 257.90–257.98) and their Part A risk mitigation plans. EPA will continue to review risk mitigation measures and may require additional…
- No Extension for Small Impoundments: cost, low. EPA is not proposing any extension for unlined CCR surface impoundments that are 40 acres or smaller; those owners/operators were required to cease coal-fired boiler operation and complete closure by October 17, 2023 and those impoundments have ceased receiving CCR and non‑CCR wastes.

## Related documents

- [2026-22082](https://policyrisk.com/federal-register/2026-22082): Additional Reconsideration Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sour…, 2026-10-29
- [2026-21155](https://policyrisk.com/federal-register/2026-21155): Renewable Fuel Standard (RFS) Program: Reallocation of Additional 2025 Small Refinery Exemptions, 2026-10-16
- [2026-20849](https://policyrisk.com/federal-register/2026-20849): Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy, 2026-10-13
- [2026-19071](https://policyrisk.com/federal-register/2026-19071): Partial Repeal of the Carbon Pollution Standards for Fossil Fuel-Fired Electric Generating Units, 2026-09-17
- [2026-19072](https://policyrisk.com/federal-register/2026-19072): Rescission of the Greenhouse Gas Findings for Fossil Fuel-Fired Power Plants and Repeal of Regulations for Power Plant Greenhouse Gas Emiss…, 2026-09-17
- [2026-18317](https://policyrisk.com/federal-register/2026-18317): Updated Definition of “Waters of the United States”, 2026-09-09

## Sources
- [2025-21597 on federalregister.gov](https://www.federalregister.gov/documents/2025/11/28/2025-21597/hazardous-and-solid-waste-management-system-disposal-of-coal-combustion-residuals-from-electric)
- [2025-21597 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-11-28/pdf/2025-21597.pdf)

## Related
- [Previous: 2025-21581, Furnishing Identifying Number of Tax Return Preparer](https://policyrisk.com/federal-register/2025-21581)
- [Next: 2025-21620, Build America: Eliminating Barriers to Wireless Deployments](https://policyrisk.com/federal-register/2025-21620)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-21597 (as of 2026-06-11).