- Document number: 2025-24119
- Title: Duke Energy Progress, LLC; H. B. Robinson Steam Electric Plant, Unit No. 2; Exemption
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 90 FR 61439
- Published: 2025-12-31
- Effective: 2025-12-23
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Nuke Plant Snags Delayed Safety Code Green Light

## Summary

Duke Energy Progress got the green light from the Nuclear Regulatory Commission to use a special inspection code (ASME Code Case N-921) a bit later than planned at the H.B. Robinson nuclear plant. This change affects the plant’s safety checks during its sixth inspection cycle but won’t cost extra or cause delays. The exemption was officially approved on December 23, 2025, keeping the plant running smoothly and safely.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a request dated May 8, 2025, as supplemented by letter dated August 21, 2025, from Duke Energy Progress, LLC, to allow the implementation of the American Society of Mechanical Engineers Code Case N-921 after the start dates of the sixth Inservice Inspection (ISI) interval at H.B. Robinson Steam Electric Plant, Unit No.2.

## Effects PRIA read

No economic effects identified for this document.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2025-24119 on federalregister.gov](https://www.federalregister.gov/documents/2025/12/31/2025-24119/duke-energy-progress-llc-h-b-robinson-steam-electric-plant-unit-no-2-exemption)
- [2025-24119 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2025-12-31/pdf/2025-24119.pdf)

## Related
- [Previous: 2025-24118, Duke Energy Carolinas, LLC; Oconee Nuclear Station Units 1, 2, and 3; Exemption](https://policyrisk.com/federal-register/2025-24118)
- [Next: 2025-24120, Modification of the Allocation of the WTO Tariff-Rate Quota Volumes for Beef](https://policyrisk.com/federal-register/2025-24120)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2025-24119 (as of 2026-06-08).