# 2026-00825: Virginia Gas Storage Plan: Weigh In on Eco Impacts

2026-00825, Columbia Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Southeast Virginia Energy Storage Project, and Notice of Public Scoping Session, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-01-16, effective 2026-01-16 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-00825
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-00825
- Title: Columbia Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Southeast Virginia Energy Storage Project, and Notice of Public Scoping Session
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 2121
- Published: 2026-01-16
- Effective: 2026-01-16
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Virginia Gas Storage Plan: Weigh In on Eco Impacts

## Summary

Columbia Gas wants to build a new energy storage project in Sussex County, Virginia, and the government is asking the public to share their thoughts on how it might affect the environment. People have until February 12, 2026, to send in comments, which will help decide if the project moves forward. This is a chance for locals and anyone interested to speak up before any big money or construction starts.

## Effects PRIA read

- Project aims to boost energy reliability: benefit, medium. You live in Virginia: Columbia Gas proposes a Southeast Virginia Energy Storage Project in Sussex County that would provide up to 1,100,000 dekatherms per day to help meet winter peak-day loads, mitigate pricing volatility during high-demand periods, and enhance regional energy reliability.
- Landowners face eminent domain risk: cost, high. If you own land in the project area, Columbia may contact you to negotiate an easement to construct and operate the facilities; you are not required to agree. If the Commission approves the project, the Natural Gas Act conveys eminent domain authority to the company, and if no agreement is reached…
- Construction will disturb 91.0 acres: cost, medium. Construction of the proposed facilities would disturb about 91.0 acres of land, and Columbia would maintain about 33.0 acres for permanent operation; the remaining acreage would be restored and revert to former uses.
- Construction may affect roads, traffic, safety: cost, medium. Commission staff identified roadway improvements necessary to access construction work areas, traffic effects, and public safety as specific issues to evaluate; construction and access could require roadwork and affect local travel and safety during the project.
- Opportunity to comment by Feb 12, 2026: benefit, low. You can submit written or oral comments on environmental issues so the Commission receives them by 5:00 p.m. Eastern Time on February 12, 2026. A public scoping session will be held on February 3, 2026, from 5:00–7:00 p.m. at Jessica Ann Moore Foundation Community Center, 408 School St., Waverly, V…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-00825 on federalregister.gov](https://www.federalregister.gov/documents/2026/01/16/2026-00825/columbia-gas-transmission-llc-notice-of-scoping-period-requesting-comments-on-environmental-issues)
- [2026-00825 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-01-16/pdf/2026-00825.pdf)

## Related
- [Previous: 2026-00824, Combined Notice of Filings](https://policyrisk.com/federal-register/2026-00824)
- [Next: 2026-00826, Records Governing Off-the-Record Communications; Public Notice](https://policyrisk.com/federal-register/2026-00826)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-00825 (as of 2026-06-08).