## Facts
- Document number: 2026-00985
- Title: Columbia Gulf Transmission, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Maysville Project
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 2338
- Published: 2026-01-20
- Effective: 2026-08-11
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Pipeline Dreams: FERC Greenlights Maysville Gas Route Check

## Summary

Columbia Gulf Transmission wants to build a new natural gas pipeline called the Maysville Project to supply energy to a power station in Kentucky. The government is getting ready to check the project’s environmental impact and will share their findings by August 11, 2026. If all goes well, final decisions and permits should be wrapped up by November 9, 2026, affecting local energy and possibly jobs.

## Effects PRIA read

- Environmental review schedule set: mixed, low. The Commission staff will issue an Environmental Assessment (EA) on August 11, 2026, and that EA will be open for a 30-day comment period. Federal agencies must reach final decisions on required federal authorizations within 90 days of the EA, by November 9, 2026.
- New gas supply: 340,000 Dth/day: benefit, medium. The Maysville Project would provide 340,000 dekatherms per day (Dth/d) of natural gas transportation capacity to East Kentucky Power Cooperative's Hugh L. Spurlock Power Station. That adds explicit new gas supply capacity intended for that power plant.
- Local land and environmental concerns raised: cost, medium. Commenters told the Commission they are concerned the 42-mile, 30-inch pipeline and related facilities could harm water quality, hydrology, wildlife habitat, cause soil erosion, affect karst features, damage historic resources and agricultural land, lower property values, raise safety concerns for…
- Project may affect local jobs: benefit, low. The notice states the project could affect local energy and possibly jobs in the area around the pipeline and the power station. The environmental review and permitting timeline runs through November 9, 2026, which is when federal authorization decisions are expected.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-00985 on federalregister.gov](https://www.federalregister.gov/documents/2026/01/20/2026-00985/columbia-gulf-transmission-llc-notice-of-schedule-for-the-preparation-of-an-environmental-assessment)
- [2026-00985 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-01-20/pdf/2026-00985.pdf)

## Related
- [Previous: 2026-00984, Southern California Edison Company; Lower Tule Hydro, LLC; Notice of Applicatio…](https://policyrisk.com/federal-register/2026-00984)
- [Next: 2026-00986, Texas Eastern Transmission, LP; Notice of Schedule for the Preparation of an En…](https://policyrisk.com/federal-register/2026-00986)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-00985 (as of 2026-06-08).