# 2026-01143: Michigan Pioneer Nuclear Units Get Phased Build Okay

2026-01143, SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application-Limited Work Authorization, is a Federal Register notice from Nuclear Regulatory Commission published 2026-01-22, effective 2026-01-22 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-01143
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-01143
- Title: SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application-Limited Work Authorization
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 2803
- Published: 2026-01-22
- Effective: 2026-01-22
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Michigan Pioneer Nuclear Units Get Phased Build Okay

## Summary

SMR, LLC has asked the Nuclear Regulatory Commission for permission to start building two new small nuclear reactors called Pioneer Units 1 and 2 in Michigan. This first step lets them do limited work while the full permit is reviewed, speeding up the project without big money moves yet. This means local communities and energy users can look forward to cleaner power in the future.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) has received the first part of a phased construction permit application, including a limited work authorization (LWA) request, from SMR, LLC (SMR), a Holtec International Company, for a dual-unit SMR-300 plant located at the Palisades Energy Center (PEC) in Covert, Michigan. The units are individually named Pioneer Unit 1 and Pioneer Unit 2.

## Effects PRIA read

- Limited Early Construction Request: benefit, low. SMR, LLC submitted a Limited Work Authorization (LWA) request to the NRC to begin certain early construction activities for two SMR-300 units named Pioneer Unit 1 and Pioneer Unit 2 at the Palisades Energy Center in Covert, Michigan. The LWA would let the applicant do limited work while the full co…
- Public Participation During NRC Review: benefit, low. If the NRC staff accepts Part 1 for docketing, the staff will begin a detailed technical review and subsequent Federal Register notices will describe opportunities for public participation during that review. This gives members of the public a formal chance to participate in the NRC review process…
- Application Available Publicly Online: benefit, low. The Part 1 LWA application and supporting documents are publicly available in the NRC's ADAMS system under Package Accession No. ML25365A983 and on the NRC website for the SMR-300 Pioneer Units. Anyone may inspect the application using the stated ADAMS accession number or the NRC web page link.
- Part Two Submission Timeline: benefit, low. SMR plans to submit Part 2 of the phased construction permit application no later than 18 months after the Part 1 submittal. Part 1 of the application was filed on December 31, 2025, making the Part 2 commitment tied to that filing date.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-01143 on federalregister.gov](https://www.federalregister.gov/documents/2026/01/22/2026-01143/smr-llc-pioneer-units-1-and-2-phased-construction-permit-application-limited-work-authorization)
- [2026-01143 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-01-22/pdf/2026-01143.pdf)

## Related
- [Previous: 2026-01142, Agency Information Collection; Request for Public Comment](https://policyrisk.com/federal-register/2026-01142)
- [Next: 2026-01144, Agency Information Collection Activities; Submission to the Office of Managemen…](https://policyrisk.com/federal-register/2026-01144)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-01143 (as of 2026-06-08).