# 2026-02034: Eugene Water & Electric Board; Notice of Intent To Prepare an Environmental Assessment

2026-02034, Eugene Water & Electric Board; Notice of Intent To Prepare an Environmental Assessment, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-02-02, effective 2026-07-31 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-02034
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-02034
- Title: Eugene Water & Electric Board; Notice of Intent To Prepare an Environmental Assessment
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 4554
- Published: 2026-02-02
- Effective: 2026-07-31
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## Summary

Eugene Water & Electric Board plans to install a new device called a load bank at the Carmen Power Plant in Oregon to protect the local river environment from water spills. This change affects people living near the McKenzie and Smith Rivers and involves an environmental check happening now, with a report due by July 31, 2026. The public can share their thoughts during a 30-day comment period after the report is released.

## Effects PRIA read

- Load Bank to Prevent River Spills: benefit, low. Eugene Water & Electric Board proposes to install a load bank at the Carmen Power Plant to protect the Smith Bypass Reach and its associated environment from spill events. The load bank would dissipate electricity equivalent to at least 800 cubic feet per second of spill; the project is located on…
- 30-Day Public Comment on EA: benefit, low. Commission staff intends to prepare an environmental assessment (EA) and plans to issue the EA by July 31, 2026. When the EA is issued it will be available for a 30-day public comment period, and all comments filed on the EA will be reviewed and considered in the Commission's final decision.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-02034 on federalregister.gov](https://www.federalregister.gov/documents/2026/02/02/2026-02034/eugene-water-and-electric-board-notice-of-intent-to-prepare-an-environmental-assessment)
- [2026-02034 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-02-02/pdf/2026-02034.pdf)

## Related
- [Previous: 2026-02032, Federal and State Current Issues Collaborative; Notice of Meeting and Agenda](https://policyrisk.com/federal-register/2026-02032)
- [Next: 2026-02035, Great River Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment](https://policyrisk.com/federal-register/2026-02035)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-02034 (as of 2026-06-08).