2026-03625, Applications for Amendments to Facility Operating Licenses Involving Proposed No Significant Hazards Consideration Determination and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information, is a Federal Register notice from Nuclear Regulatory Commission published 2026-02-24, effective 2026-02-24 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-03625
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-03625
- Title: Applications for Amendments to Facility Operating Licenses Involving Proposed No Significant Hazards Consideration Determination and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 8916
- Published: 2026-02-24
- Effective: 2026-02-24
- Comments close: 2026-03-26
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

NRC Reviews Safe License Updates for Nuclear Plants

## Summary

The Nuclear Regulatory Commission is reviewing requests to update operating licenses for several nuclear power plants, including Braidwood, Byron, Virgil C. Summer, and Salem stations. These updates are considered safe with no big risks and include sensitive info that needs special access rules. If you want to comment or get involved, act by late March or April 2026—no big costs, just your voice and attention!

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) received and is considering approval of a request to amend three operating licenses. The license amendment requests are for Braidwood Station, Units 1 and 2, and Byron Station, Unit Nos. 1 and 2; Virgil C. Summer Nuclear Station, Unit 1; and Salem Nuclear Generating Station, Unit Nos. 1 and 2. For each amendment request, the NRC proposes to determine that it involves no significant hazards consideration (NSHC). Because each amendment request contains sensitive unclassified non-safeguards information (SUNSI), the NRC is issuing an order imposing procedures to obtain access to SUNSI for contention preparation by persons who file a hearing request or petition for leave to intervene.

## Effects PRIA read

- Deadlines to Comment or Request Hearing: benefit, low. You can submit public comments on these license amendment requests by March 26, 2026, and you must file any request for a hearing or petition for leave to intervene by April 27, 2026. Any person whose interest may be affected has 60 days from publication to file a petition to intervene under 10 CFR…
- How to Access Sensitive SUNSI Documents: benefit, low. If you need access to Sensitive Unclassified Non-Safeguards Information (SUNSI) to prepare a contention, you must request access within 10 days of this notice (by March 6, 2026), explain your standing and need, and the NRC staff will decide within 10 days whether to grant access. If access is grant…
- Salem Station May Produce Cobalt-60: mixed, low. PSEG's proposed amendment for Salem Nuclear Generating Station, Units 1 and 2 would revise the renewed facility operating licenses to allow receipt, production, transfer, and use of Cobalt-60 (Co-60) intended for industrial and medical purposes, and the NRC has preliminarily determined this amendme…
- Commission May Issue Amendments Quickly: cost, low. The NRC normally waits 60 days after publication before issuing license amendments, but it may issue an amendment earlier if it finds no significant hazards consideration or if delay would cause derating or shutdown. If the final NSHC determination is made, any hearing will occur after issuance.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-03625 on federalregister.gov](https://www.federalregister.gov/documents/2026/02/24/2026-03625/applications-for-amendments-to-facility-operating-licenses-involving-proposed-no-significant-hazards)
- [2026-03625 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-02-24/pdf/2026-03625.pdf)

## Related
- [Previous: 2026-03624, Notice of Adoption of Categorical Exclusions Under the National Environmental P…](https://policyrisk.com/federal-register/2026-03624)
- [Next: 2026-03626, Constellation Energy Generation, LLC; Christopher M. Crane Clean Energy Center;…](https://policyrisk.com/federal-register/2026-03626)
- [All Federal Register documents](https://policyrisk.com/federal-register)