# 2026-04327: NRC Lets Nuclear Site Delay Radioactive Report Deadlines Without a Hitch

2026-04327, Holtec Decommissioning International, LLC; Big Rock Point Independent Spent Fuel Storage Installation; Exemption, is a Federal Register notice from Nuclear Regulatory Commission published 2026-03-05, effective 2026-02-17 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-04327
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-04327
- Title: Holtec Decommissioning International, LLC; Big Rock Point Independent Spent Fuel Storage Installation; Exemption
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 10833
- Published: 2026-03-05
- Effective: 2026-02-17
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

NRC Lets Nuclear Site Delay Radioactive Report Deadlines Without a Hitch

## Summary

The Nuclear Regulatory Commission gave Holtec Decommissioning International permission to change when they submit their yearly report on radioactive releases at the Big Rock Point spent fuel storage site. This means Holtec can submit the report on a different schedule than usual, helping them manage their paperwork better without extra costs or delays. The exemption started on February 17, 2026, and affects how Holtec handles safety reporting for stored nuclear fuel.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) has issued an exemption to Holtec Decommissioning International, LLC, (HDI), for Big Rock Point (BRP) independent spent fuel storage installation (ISFSI). The exemption allows BRP ISFSI to deviate from the requirements in Certificate of Compliance (CoC) No. 1026, Amendment No. 4, appendix A, technical specifications (TS) for the FuelSolutions\TM\ Storage System, section 5.3.4, "Radioactive Effluent Control Program," subsection 5.3.4.3, related to the timing of submission for its Annual Radioactive Effluent Release Report (ARERR).

## Effects PRIA read

No economic effects identified for this document.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-04327 on federalregister.gov](https://www.federalregister.gov/documents/2026/03/05/2026-04327/holtec-decommissioning-international-llc-big-rock-point-independent-spent-fuel-storage-installation)
- [2026-04327 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-03-05/pdf/2026-04327.pdf)

## Related
- [Previous: 2026-04326, National Cancer Institute; Amended Notice of Meeting](https://policyrisk.com/federal-register/2026-04326)
- [Next: 2026-04328, Certain Cold-Rolled Steel Flat Products From Republic of Korea: Preliminary Res…](https://policyrisk.com/federal-register/2026-04328)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-04327 (as of 2026-06-08).