# 2026-04550: Gas Pipeline in Kansas: Send Your Eco-Complaints by April!

2026-04550, Southern Star Central Gas Pipeline, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Viola Project, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-03-09, effective 2026-04-03; PRIA reads it as touching household money (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-04550
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-04550
- Title: Southern Star Central Gas Pipeline, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Viola Project
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 11296
- Published: 2026-03-09
- Effective: 2026-04-03
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Gas Pipeline in Kansas: Send Your Eco-Complaints by April!

## Summary

Southern Star wants to build new gas pipeline facilities in Sumner County, Kansas, and the government is asking the public to share their thoughts on how this might affect the environment. People have until April 3, 2026, to send in comments about possible impacts and ideas to reduce harm. This feedback will help decide if the project moves forward and how it might change the area.

## Effects PRIA read

- Easement Offers and Eminent Domain Risk: cost, high. If you own land in the project area, Southern Star may contact you to negotiate an easement to construct, operate, and maintain the pipeline. You do not have to agree, but if FERC approves the project the Natural Gas Act conveys eminent domain rights to the company, which could initiate condemnatio…
- Construction Disturbance and Permanent Land Use: cost, medium. Construction of the Viola Project would disturb about 266.4 acres of land and Southern Star would permanently maintain about 163.8 acres for operation of the pipeline and aboveground facilities. That means substantial temporary disturbance during construction and a defined amount of land kept in pe…
- Formal Environmental and Historic Review: benefit, medium. FERC staff will prepare an environmental document (an Environmental Assessment or an Environmental Impact Statement) that will evaluate effects on geology and soils; water resources and wetlands; vegetation and wildlife; threatened and endangered species; cultural resources; land use; socioeconomic…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-04550 on federalregister.gov](https://www.federalregister.gov/documents/2026/03/09/2026-04550/southern-star-central-gas-pipeline-inc-notice-of-scoping-period-requesting-comments-on-environmental)
- [2026-04550 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-03-09/pdf/2026-04550.pdf)

## Related
- [Previous: 2026-04549, Neenah Paper FR, LLC, Appleton Dam, LLC; Notice of Application of Transfer of L…](https://policyrisk.com/federal-register/2026-04549)
- [Next: 2026-04551, Sugar River Hydro II, LLC; Notice of Revised Schedule for Environmental Assessm…](https://policyrisk.com/federal-register/2026-04551)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-04550 (as of 2026-06-08).