# 2026-04551: Hydro Project Shutdown Delayed: Dam Stays, Power Goes Away

2026-04551, Sugar River Hydro II, LLC; Notice of Revised Schedule for Environmental Assessment, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-03-09, effective 2026-03-04 (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-04551
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-04551
- Title: Sugar River Hydro II, LLC; Notice of Revised Schedule for Environmental Assessment
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 11304
- Published: 2026-03-09
- Effective: 2026-03-04
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Hydro Project Shutdown Delayed: Dam Stays, Power Goes Away

## Summary

Sugar River Hydro II, LLC is planning to shut down its hydroelectric project in New Hampshire by removing key equipment and closing the penstock, but keeping the dam in place. The Environmental Assessment, originally due in March 2026, is now delayed until July 10, 2026, giving more time for reviews and public comments. This change affects local agencies, the company, and the community, with no new costs announced yet.

## Effects PRIA read

- Environmental Assessment Delayed: benefit, low. The Federal Energy Regulatory Commission staff moved the Environmental Assessment (EA) deadline to July 10, 2026. The EA will be published with a 30-day comment period, and all comments filed during that period will be reviewed and considered in the Commission's final decision.
- Project Equipment Removal Plan: mixed, medium. Sugar River Hydro II, LLC plans to disconnect generator leads; remove transformers, other electrical equipment, hydraulic and governor fluids and reservoirs; remove project operating equipment and monitors from the dam; secure the powerhouse; and close the penstock intake while keeping the dam and…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-04551 on federalregister.gov](https://www.federalregister.gov/documents/2026/03/09/2026-04551/sugar-river-hydro-ii-llc-notice-of-revised-schedule-for-environmental-assessment)
- [2026-04551 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-03-09/pdf/2026-04551.pdf)

## Related
- [Previous: 2026-04550, Southern Star Central Gas Pipeline, Inc.; Notice of Scoping Period Requesting C…](https://policyrisk.com/federal-register/2026-04550)
- [Next: 2026-04552, Texas Eastern Transmission, LP; Notice of Scoping Period Requesting Comments on…](https://policyrisk.com/federal-register/2026-04552)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-04551 (as of 2026-06-08).