# 2026-05711: FERC Bolsters Cyber Defenses for Low-Impact Power Grids

2026-05711, Order No. 918; Critical Infrastructure Protection Reliability Standard CIP-003-11-Cyber Security-Security Management Controls, is a Federal Register rule from Energy Department, Federal Energy Regulatory Commission published 2026-03-24, effective 2026-05-26; PRIA reads it as touching household money (as of 2026-06-11).

- Canonical: https://policyrisk.com/federal-register/2026-05711
- As of: 2026-06-11
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-05711
- Title: Order No. 918; Critical Infrastructure Protection Reliability Standard CIP-003-11-Cyber Security-Security Management Controls
- Type: Rule
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 13952
- Published: 2026-03-24
- Effective: 2026-05-26
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-06-11

## In one line

FERC Bolsters Cyber Defenses for Low-Impact Power Grids

## Summary

The Federal Energy Regulatory Commission just approved a new cyber security rule called CIP-003-11 to better protect smaller electric facilities from cyberattacks. This update affects companies running low-impact electric systems and kicks in on May 26, 2026. It helps keep the power grid safer without adding big costs, by tightening security controls where it counts.

## Abstract

The Federal Energy Regulatory Commission (Commission) approves the proposed Critical Infrastructure Protection (CIP) Reliability Standard CIP-003-11 (Cyber Security--Security Management Controls). The North American Electric Reliability Corporation (NERC), the Commission- certified Electric Reliability Organization (ERO), submitted the proposed Reliability Standard to mitigate risks posed by a coordinated cyberattack on low-impact facilities, the aggregate impact of which could be much greater.

## Effects PRIA read

- Stronger power-grid cyber defenses: benefit, high. The Commission approved Reliability Standard CIP-003-11 to strengthen cybersecurity protections for low-impact bulk electric system (BES) cyber systems, improving the reliability of the bulk electric system. The rule is effective May 26, 2026 and the Commission found the Standard "improves the reli…
- New low-impact cybersecurity controls required: cost, medium. CIP-003-11 requires registered entities responsible for low-impact BES Cyber Systems to implement controls that authenticate remote users, protect authentication information in transit, and detect malicious communications to or between assets with external routable connectivity. These operational r…
- Paperwork and compliance burden for 1,673 entities: cost, high. All 1,673 U.S. entities on the NERC Compliance Registry subject to CIP Standards must conform to CIP-003-11 and maintain documentation for audits. The Commission estimates a total annualized burden of 257,642 hours and a total cost of $24,991,274 (total for FERC-725B(5) under CIP-003-11), with an a…
- Estimated per-small-entity implementation cost: cost, high. The Commission estimates 406 of the affected entities are small entities; each of those 406 small entities will incur an estimated one-time implementation cost of approximately $19,000 plus an ongoing paperwork burden of $14,938 over Years 1-3, for a total estimated cost of $33,938 per small entity…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-05711 on federalregister.gov](https://www.federalregister.gov/documents/2026/03/24/2026-05711/order-no-918-critical-infrastructure-protection-reliability-standard-cip-003-11-cyber)
- [2026-05711 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-03-24/pdf/2026-05711.pdf)

## Related
- [Previous: 2026-05709, Order No. 917; Filing Process and Data Collection for the Electric Quarterly Re…](https://policyrisk.com/federal-register/2026-05709)
- [Next: 2026-05712, Approval and Promulgation of Delegation of Authority for Designated Facilities…](https://policyrisk.com/federal-register/2026-05712)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-05711 (as of 2026-06-11).