# 2026-06773: TVA Greenlights Massive Solar Farm in Alabama's Backyard

2026-06773, Spring Valley II Solar Final Environmental Impact Statement, is a Federal Register notice from Tennessee Valley Authority published 2026-04-08, effective 2026-03-26; PRIA reads it as touching household money (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-06773
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-06773
- Title: Spring Valley II Solar Final Environmental Impact Statement
- Type: Notice
- Agencies: Tennessee Valley Authority
- Citation: 91 FR 17824
- Published: 2026-04-08
- Effective: 2026-03-26
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

TVA Greenlights Massive Solar Farm in Alabama's Backyard

## Summary

The Tennessee Valley Authority (TVA) is moving forward with a big solar project in Colbert County, Alabama, to help meet growing energy needs. They’ll buy power from a new 200-megawatt solar farm covering 740 acres, plus build a substation and upgrade power lines to connect it all. This clean energy boost supports local communities and fits TVA’s plan to provide reliable, greener electricity without using taxpayer money.

## Abstract

The Tennessee Valley Authority (TVA) has decided to adopt the preferred alternative identified in its final environmental impact statement (Final EIS; Document ID EISX-455-00-000-1729685609) for the Spring Valley II Solar Project. The Final EIS was made available to the public on December 19, 2025. A Notice of Availability (NOA) of the Final EIS was published in the Federal Register on January 2, 2026 (91 FR 1). TVA's preferred alternative, analyzed in the Final EIS as the Proposed Action Alternative, consists of TVA executing a power purchase agreement (PPA) with Spring Valley Solar, LLC (Spring Valley Solar), a wholly owned subsidiary of Urban Grid, to purchase power generated by an approximately 200-megawatt (MW) alternating current (AC) solar photovoltaic (PV) facility, which would occupy approximately 740 acres of a 2,426-acre Project Site, in Colbert County, Alabama, south of the city limits of Tuscumbia, Alabama, near the City of Muscle Shoals and Florence, Alabama, along US Highway 43. To interconnect to TVA's existing electrical grid Spring Valley Solar, LLC, would build a new onsite 161-kV substation and install network upgrades to the nearby transmission lines (TL). This alternative would achieve the purpose and need of the Project to meet the energy needs in response to customer demands and aligns with TVA's 2019 Integrated Resource Plan (IRP).

## Effects PRIA read

- TVA signs 20-year solar power deal: benefit, low. TVA will execute a 20-year power purchase agreement (PPA) to buy electricity from a new approximately 200-megawatt (MW) AC solar photovoltaic facility that would occupy about 740 acres in Colbert County, Alabama. To connect the plant, Spring Valley Solar will build an onsite 161-kV substation and m…
- 740 acres used, farmland impacts noted: mixed, medium. About 740 acres of a 2,426-acre Project Site in Colbert County, Alabama will be used for the solar facility, and the Final EIS notes the Proposed Action could have moderate impacts on prime farmland. After the 20-year PPA ends, the site could be returned to agricultural use with little reduction in…
- Visual and cultural screening required: benefit, low. The project must maintain a minimum 50-foot setback along property lines and a 30-foot-wide native vegetated buffer around the solar facility, and implement specific visual-screening measures near the Belle Mont Mansion (including new plantings and green mesh fence screening). TVA and Spring Valley…
- Minor local socioeconomic benefits expected: benefit, low. The Final EIS states the Proposed Action would have minor beneficial impacts to socioeconomics in the project area. TVA also notes the project aligns with its 2019 Integrated Resource Plan to expand renewable capacity through 2038.

## Related documents

- [2026-14605](https://policyrisk.com/federal-register/2026-14605): Generator Interconnection Programmatic Environmental Impact Statement, 2026-07-20
- [2026-13108](https://policyrisk.com/federal-register/2026-13108): Agency Information Collection Activities: Submission for OMB Review; Comment Request, 2026-06-30
- [2026-08661](https://policyrisk.com/federal-register/2026-08661): Meeting of the Regional Resource Stewardship Council, 2026-05-05
- [2025-06830](https://policyrisk.com/federal-register/2025-06830): Chatuge Dam Safety Modifications, 2025-04-21
- [2025-05270](https://policyrisk.com/federal-register/2025-05270): Sugar Camp Energy, LLC Mine No. 1 Significant Boundary Revision 8 Environmental Impact Statement, 2025-03-27
- [2025-04066](https://policyrisk.com/federal-register/2025-04066): Hope Solar and Storage Project, 2025-03-13

## Sources
- [2026-06773 on federalregister.gov](https://www.federalregister.gov/documents/2026/04/08/2026-06773/spring-valley-ii-solar-final-environmental-impact-statement)
- [2026-06773 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-04-08/pdf/2026-06773.pdf)

## Related
- [Previous: 2026-06772, Notice: System End-of-Life Status](https://policyrisk.com/federal-register/2026-06772)
- [Next: 2026-06774, Meeting of the Regional Energy Resource Council](https://policyrisk.com/federal-register/2026-06774)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-06773 (as of 2026-06-08).