## Facts
- Document number: 2026-08055
- Title: Pipeline Safety: Consent Orders.
- Type: Rule
- Agencies: Transportation Department; Pipeline and Hazardous Materials Safety Administration
- Citation: 91 FR 21970
- Published: 2026-04-24
- Effective: 2026-04-24
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: 2137-AG42
- Last updated: 2026-06-11

## In one line

Pipeline Fines? Settle Faster with New PHMSA Consent Order Rules

## Summary

Starting April 24, 2026, pipeline companies and anyone involved in pipeline safety enforcement can settle all enforcement cases, even those with fines, through consent agreements. This change makes resolving issues faster and clearer, saving time and possibly money by avoiding long disputes. It’s a win-win for safety and smoother enforcement!

## Abstract

PHMSA is amending its procedural regulations to clarify that consent agreements may be used to resolve all PHMSA enforcement proceedings, including cases with civil penalties.

## Effects PRIA read

- Settle Any PHMSA Enforcement Case: benefit, medium. Starting April 24, 2026, PHMSA clarifies that consent agreements and orders may be used to resolve any enforcement proceeding brought under 49 CFR part 190, subpart B, including cases that involve civil penalties. This means pipeline operators and others in enforcement proceedings can agree to sett…
- Consent Orders Become Final Orders: benefit, low. The rule states that when a consent agreement and order is executed under Sec. 190.219, that consent order is treated as a final order under Sec. 190.213. This makes the settlement legally final once both parties execute the consent order.
- No New Requirements; Clarifies Practice: benefit, low. PHMSA says the amendments are non-substantive, codify current informal practices, and do not impose new requirements on pipeline operators. The agency states it expects no significant costs and that the clarification will likely reduce regulatory burdens and improve uniformity in petition processes.
- Can Request Consent Order As Response: benefit, low. The rule adds a response option in Sec. 190.208(a)(3) allowing respondents to request the execution of a consent order under Sec. 190.219. This gives parties receiving enforcement notices an explicit procedural option to ask for a settlement agreement.

## Related documents

- [2026-22396](https://policyrisk.com/federal-register/2026-22396): Pipeline Safety: Amendments to Liquefied Natural Gas Facilities, 2026-11-03
- [2026-13805](https://policyrisk.com/federal-register/2026-13805): Pipeline Safety: Repair Criteria for Hazardous Liquid and Gas Transmission Pipelines, 2026-07-08
- [2026-10969](https://policyrisk.com/federal-register/2026-10969): Pipeline Safety: Breakout Tank Inspection Rule, 2026-06-02
- [2026-10782](https://policyrisk.com/federal-register/2026-10782): Pipeline Safety: Class Location Change Requirements; Correction, 2026-05-29
- [2026-08144](https://policyrisk.com/federal-register/2026-08144): Administrative Rulemaking, Guidance, and Enforcement Procedures, 2026-04-27
- [2026-08058](https://policyrisk.com/federal-register/2026-08058): Pipeline Safety: Safety of Gas Transmission Pipelines: MAOP Reconfirmation, Expansion of Assessment Requirements, and Other Related Amendme…, 2026-04-24

## Sources
- [2026-08055 on federalregister.gov](https://www.federalregister.gov/documents/2026/04/24/2026-08055/pipeline-safety-consent-orders)
- [2026-08055 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-04-24/pdf/2026-08055.pdf)

## Related
- [Previous: 2026-08054, Pipeline Safety: Declaratory Order Procedures](https://policyrisk.com/federal-register/2026-08054)
- [Next: 2026-08056, Pipeline Safety: Electronic Submission of Requests for Written Interpretations…](https://policyrisk.com/federal-register/2026-08056)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-08055 (as of 2026-06-11).