# 2026-09425: Kentucky's Landscape Faces Pumped Storage Environmental Deep Dive

2026-09425, Lewis Ridge Pumped Storage, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Lewis Ridge Pumped Storage Project, Schedule for Environmental Review, and Request for Comments, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-05-12; PRIA reads it as touching household money (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-09425
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-09425
- Title: Lewis Ridge Pumped Storage, LLC; Notice of Intent To Prepare an Environmental Impact Statement for the Lewis Ridge Pumped Storage Project, Schedule for Environmental Review, and Request for Comments
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 25878
- Published: 2026-05-12
- Effective: unknown
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Kentucky's Landscape Faces Pumped Storage Environmental Deep Dive

## Summary

The Federal Energy Regulatory Commission is getting ready to study how building and running the Lewis Ridge Pumped Storage Project in Bell County, Kentucky, might affect the environment. This project could change local landscapes and energy use, so the Commission wants to hear from the public before making decisions. They’re working on a detailed report and asking for more comments soon, aiming to keep things on track and clear for everyone involved.

## Effects PRIA read

- Tom Fork River inundation and water use: cost, medium. If you live in Kentucky near Bell County, the lower reservoir would inundate part of the 1.8-mile Tom Fork River. The project requires about 2,808 acre-feet for initial fill, 149 acre-feet annually for recharge, and would only make flows above 2.8 cubic feet per second available for maintenance; ab…
- Private land and land-use changes: cost, medium. If you own property in Bell County, Kentucky, about 148 acres of privately owned land and roughly 16 additional private parcels would be inside the project boundary, and the project would build permanent and temporary roads (about 7.1 miles permanent, 4 miles temporary). The project would create a…
- Construction impacts on local economy and air/noise: mixed, medium. If you live near the project area in Bell County, construction and operation could change the local economy and cause noise, vibrations, and air-quality effects during work. The Commission specifically lists changes to local economics, noise/vibrations, and air quality as potential effects during c…
- Potential public safety from water releases: cost, medium. If you are near project reservoirs in Bell County, the project would include emergency release features and water-surface fluctuations (upper reservoir about 74 feet, lower reservoir about 100 feet), and staff identified public safety risks from potential project-related water releases. The lower r…
- New 308 MW pumped-storage adds peak power: benefit, medium. The project would include two 154-megawatt reversible pump-turbines for a total rated capacity of 308 MW and could produce about 717,000 megawatt-hours of peak energy annually. It would operate by pumping during off-peak and generating during peak periods and is intended to provide on-peak hydroele…

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-09425 on federalregister.gov](https://www.federalregister.gov/documents/2026/05/12/2026-09425/lewis-ridge-pumped-storage-llc-notice-of-intent-to-prepare-an-environmental-impact-statement-for-the)
- [2026-09425 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-05-12/pdf/2026-09425.pdf)

## Related
- [Previous: 2026-09424, Hazardous Materials: Notice of Actions on Special Permits](https://policyrisk.com/federal-register/2026-09424)
- [Next: 2026-09426, Northern Illinois Hydropower, LLC; Notice of Waiver Period for Water Quality Ce…](https://policyrisk.com/federal-register/2026-09426)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-09425 (as of 2026-06-08).