2026-09884, Takes of Marine Mammals Incidental to Specified Activities; Taking Marine Mammals Incidental to the Interstate Bridge Replacement Project on Interstate 5 between Portland, OR, and Vancouver, WA, is a Federal Register rule from Commerce Department, National Oceanic and Atmospheric Administration published 2026-05-18, effective 2027-09-15; PRIA reads it as touching household money (as of 2026-06-11).

- Canonical: https://policyrisk.com/federal-register/2026-09884
- As of: 2026-06-11
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-09884
- Title: Takes of Marine Mammals Incidental to Specified Activities; Taking Marine Mammals Incidental to the Interstate Bridge Replacement Project on Interstate 5 between Portland, OR, and Vancouver, WA
- Type: Rule
- Agencies: Commerce Department; National Oceanic and Atmospheric Administration
- Citation: 91 FR 28443
- Published: 2026-05-18
- Effective: 2027-09-15
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: 0648-BN34
- Last updated: 2026-06-11

## In one line

Bridge Builders Get Permission to Gently Disturb Local Whales

## Summary

The Interstate Bridge Replacement Project on I-5 between Portland, OR, and Vancouver, WA, will run from September 2027 to September 2032. During construction, some marine mammals might be disturbed, but NOAA has set rules to keep impacts as low as possible. This plan includes monitoring and reporting to protect local wildlife while upgrading the bridge.

## Abstract

NMFS, upon request from the Interstate Bridge Replacement Program (IBRP), issues this final rule and associated 5-year letter of authorization (LOA) pursuant to the Marine Mammal Protection Act (MMPA), to govern the taking of marine mammals incidental to construction activities conducted in support of the Interstate Bridge Replacement Project (IBR Project) on Interstate 5 (I-5) between Portland, Oregon, and Vancouver, Washington, over the course of 5 years. This final rule prescribes the permissible methods of taking and other means of effecting the least practicable adverse impact on marine mammal species and their habitat and establishes requirements pertaining to the monitoring and reporting of such taking.

## Effects PRIA read

- Five-year LOA authorizes work: benefit, medium. NOAA issued a 5-year rule and Letter of Authorization (LOA) that allows the Interstate Bridge Replacement Project to conduct in-water construction between September 15, 2027 and September 14, 2032. The LOA sets the legal permission for pile driving and other in-water work during that period, subjec…
- Work timing, pile counts, schedule: cost, high. The rule limits impact pile driving to the annual in-water window September 15 through April 15 and allows vibratory driving year-round. For the first 5 years the project anticipates about 1,725 non-consecutive in-water work days, installation of approximately 1,560 temporary steel pipe piles and 1…
- Required noise mitigation and testing: cost, medium. For impact pile driving in water depths >0.67 m the project must use bubble curtains that cover 100% of the pile circumference and contact the substrate, and perform hydroacoustic monitoring of impact driving. Up to 75 unattenuated test strikes may be required (about 10 minutes, ~1 day per week) wi…
- Monitoring, PSO and reporting duties: cost, medium. The IBRP must employ NMFS-approved protected species observers (PSOs) for all pile driving activities, with pre-start clearance monitoring 30 minutes before work and 30 minutes after, and maintain at least two monitoring locations when practicable. Daily monitoring and reporting must record dates,…
- Potential ironworker employment boost: benefit, low. A comment submitted in the rulemaking expressed support for the IBR Project and noted potential increases in employment and training opportunities for ironworkers associated with the bridge construction. NMFS reported that one comment letter made this point.

## Related documents

- [2026-14204](https://policyrisk.com/federal-register/2026-14204): Lake Ontario National Marine Sanctuary; Delay of Effective Date, 2026-07-15
- [2026-14195](https://policyrisk.com/federal-register/2026-14195): Rescinding the Definition of “Harm” Under the Endangered Species Act, 2026-07-14
- [2026-07536](https://policyrisk.com/federal-register/2026-07536): Taking and Importing Marine Mammals; Taking Marine Mammals Incidental to Geophysical Surveys in the Gulf of America, 2026-04-17
- [2026-05599](https://policyrisk.com/federal-register/2026-05599): Deep Seabed Mining: Notice of Receipt of Applications for Deep Seabed Mining Exploration Licenses and Announcement of Public Comment Period…, 2026-03-23
- [2026-04256](https://policyrisk.com/federal-register/2026-04256): Atlantic Highly Migratory Species; Spatial Fisheries Management; Amendment 15 to the 2006 Consolidated Atlantic Highly Migratory Species Fi…, 2026-03-04
- [2025-12513](https://policyrisk.com/federal-register/2025-12513): Deep Seabed Mining: Revisions to Regulations for Exploration License and Commercial Recovery Permit Applications, 2025-07-07

## Sources
- [2026-09884 on federalregister.gov](https://www.federalregister.gov/documents/2026/05/18/2026-09884/takes-of-marine-mammals-incidental-to-specified-activities-taking-marine-mammals-incidental-to-the)
- [2026-09884 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-05-18/pdf/2026-09884.pdf)

## Related
- [Previous: 2026-09872, Special Local Regulation, Temporary Anchorage Ground Suspension, and Security Z…](https://policyrisk.com/federal-register/2026-09872)
- [Next: 2026-09973, Fisheries Off West Coast States; West Coast Salmon Fisheries; 2026 Specificatio…](https://policyrisk.com/federal-register/2026-09973)