# 2026-09901: Louisiana Seeks Input on Coastal Restoration Plans

2026-09901, Deepwater Horizon Louisiana Trustee Implementation Group Draft Phase 2 Restoration Plan and Environmental Assessment #8.1: East Orleans Landbridge Restoration and Raccoon Island Restoration, is a Federal Register notice from Commerce Department, National Oceanic and Atmospheric Administration published 2026-05-18, effective The Louisiana TIG will consider public comments on the Draft RP/ EA #8.1 received on or before June 17, 2026. (as of 2026-06-08).

- Canonical: https://policyrisk.com/federal-register/2026-09901
- As of: 2026-06-08
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-09901
- Title: Deepwater Horizon Louisiana Trustee Implementation Group Draft Phase 2 Restoration Plan and Environmental Assessment #8.1: East Orleans Landbridge Restoration and Raccoon Island Restoration
- Type: Notice
- Agencies: Commerce Department; National Oceanic and Atmospheric Administration
- Citation: 91 FR 28574
- Published: 2026-05-18
- Effective: The Louisiana TIG will consider public comments on the Draft RP/ EA #8.1 received on or before June 17, 2026.
- Comments close: 2026-06-17
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-08

## In one line

Louisiana Seeks Input on Coastal Restoration Plans

## Summary

The Louisiana Trustee group is planning to restore wetlands and coastal areas hurt by the Deepwater Horizon oil spill, focusing on East Orleans Landbridge and Raccoon Island. They’ve picked two main plans that could cost about $247 million and want your thoughts by June 17, 2026. This effort will help wildlife and communities bounce back stronger and healthier.

## Abstract

The Deepwater Horizon (DWH) natural resource Trustees for the Louisiana Trustee Implementation Group (Louisiana TIG) have prepared the Draft Phase 2 Restoration Plan and Environmental Assessment #8.1: East Orleans Landbridge Restoration Project and Raccoon Island Restoration Project (RP/EA #8.1). The Draft RP/EA #8.1 proposes alternatives to help restore wetlands, coastal, and nearshore habitats impacted by the DWH oil spill. The Draft RP/EA #8.1 evaluates three design alternatives for each project under the Oil Pollution Act (OPA) including criteria set forth in the OPA Natural Resource Damage Assessment (NRDA) regulations, and the National Environmental Policy Act of 1969 (NEPA, as amended). The total estimated cost to implement the Louisiana TIG's two preferred alternatives is approximately $246.7 million. The Louisiana TIG invites the public to comment on the Draft RP/EA #8.1.

## Effects PRIA read

- East Orleans Landbridge Restoration: benefit, medium. If you live in coastal Louisiana near East Orleans, the preferred plan would dredge and place about 5.0 million cubic yards (3.8 million m3) of sediment to restore up to 1,320 acres (534 hectares) of wetland and build about 14,867 feet (4.53 km) of shoreline protection. The estimated cost to build…
- Raccoon Island Barrier-Island Restoration: benefit, medium. If you live in coastal Louisiana near Raccoon Island, the preferred plan would dredge about 2.9 million cubic yards (2.2 million m3) of sand from an offshore source to restore up to 410 acres (166 hectares) of barrier island habitat, maintain existing Gulfside breakwaters, build four bayside breakw…
- Funding, Public Comment, and Next Steps: benefit, low. The two preferred alternatives together are estimated to cost about $246.7 million and would be funded from the Wetlands, Coastal, and Nearshore Habitats Restoration Type allocation. The Louisiana Trustee Implementation Group is accepting public comments on the Draft RP/EA #8.1 through June 17, 202…

## Related documents

- [2026-14204](https://policyrisk.com/federal-register/2026-14204): Lake Ontario National Marine Sanctuary; Delay of Effective Date, 2026-07-15
- [2026-14195](https://policyrisk.com/federal-register/2026-14195): Rescinding the Definition of “Harm” Under the Endangered Species Act, 2026-07-14
- [2026-07536](https://policyrisk.com/federal-register/2026-07536): Taking and Importing Marine Mammals; Taking Marine Mammals Incidental to Geophysical Surveys in the Gulf of America, 2026-04-17
- [2026-05599](https://policyrisk.com/federal-register/2026-05599): Deep Seabed Mining: Notice of Receipt of Applications for Deep Seabed Mining Exploration Licenses and Announcement of Public Comment Period…, 2026-03-23
- [2026-04256](https://policyrisk.com/federal-register/2026-04256): Atlantic Highly Migratory Species; Spatial Fisheries Management; Amendment 15 to the 2006 Consolidated Atlantic Highly Migratory Species Fi…, 2026-03-04
- [2025-12513](https://policyrisk.com/federal-register/2025-12513): Deep Seabed Mining: Revisions to Regulations for Exploration License and Commercial Recovery Permit Applications, 2025-07-07

## Sources
- [2026-09901 on federalregister.gov](https://www.federalregister.gov/documents/2026/05/18/2026-09901/deepwater-horizon-louisiana-trustee-implementation-group-draft-phase-2-restoration-plan-and)
- [2026-09901 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-05-18/pdf/2026-09901.pdf)

## Related
- [Previous: 2026-09899, Notice of Public Meeting To Prepare for International Maritime Organization TC…](https://policyrisk.com/federal-register/2026-09899)
- [Next: 2026-09902, Silicomanganese From India: Final Results of Antidumping Duty Administrative Re…](https://policyrisk.com/federal-register/2026-09902)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-09901 (as of 2026-06-08).