## Facts
- Document number: 2026-12228
- Title: Texas Gas Transmission, LLC; Notice of Application and Establishing Intervention Deadline
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 36819
- Published: 2026-06-18
- Effective: 2026-07-06
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-06-25

## In one line

Company Files for New Ohio Gas Pipeline Expansion

## Summary

Texas Gas Transmission wants to build a new 12-mile natural gas pipeline to deliver fuel to Vistra’s Miami Fort Power Plant in Ohio. This $86 million project will boost gas delivery by 265,000 dekatherms per day and comes with a new rate for the added service. If you’re interested, you’ve got 90 days to speak up or get involved!

## Effects PRIA read

- Pipeline to fuel Miami Fort Plant: mixed, medium. Texas Gas proposes building a new roughly 12-mile, 20-inch natural gas delivery lateral to supply Vistra Corporation’s Miami Fort Power Plant. The project would create 265,000 dekatherms per day of firm natural gas transportation service and is estimated to cost $86,247,503.
- New rate for added pipeline capacity: mixed, medium. Texas Gas proposes a new incremental recourse rate that would apply to the Project capacity created by the lateral. The application on file with the Commission includes the proposed new rate for the added service.
- 90-day public comment and intervention deadline: benefit, low. Members of the public can file comments, protests, or motions to intervene with no fee. The deadline to file a motion to intervene or to submit comments or protests is 5:00 p.m. Eastern Time on July 6, 2026, and FERC offers eComment, eFiling, and paper filing options.
- Clean Water Act Section 401 certifications required: cost, low. Texas Gas stated that a Clean Water Act section 401 water quality certification is required from the Kentucky Energy and Environment Cabinet--Department of Environmental Protection and the Indiana Department of Environmental Management. Texas Gas must submit to the Commission a copy of the request…
- FERC environmental review timing and 90‑day authorization window: mixed, medium. Within 90 days of this notice, FERC staff will either complete its environmental review and place it in the public record or issue a Notice of Schedule for Environmental Review. If an EA or FEIS is issued, federal and state agencies will be notified and must complete all necessary federal authoriza…

## Related documents

- [2026-20744](https://policyrisk.com/federal-register/2026-20744): Combined Notice of Filings #2, 2026-10-09
- [2026-20658](https://policyrisk.com/federal-register/2026-20658): Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, an…, 2026-10-08
- [2026-20659](https://policyrisk.com/federal-register/2026-20659): Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline, 2026-10-08
- [2026-20642](https://policyrisk.com/federal-register/2026-20642): Combined Notice of Filings, 2026-10-08
- [2026-20580](https://policyrisk.com/federal-register/2026-20580): Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonm…, 2026-10-08
- [2026-20582](https://policyrisk.com/federal-register/2026-20582): Combined Notice of Filings, 2026-10-08

## Sources
- [2026-12228 on federalregister.gov](https://www.federalregister.gov/documents/2026/06/18/2026-12228/texas-gas-transmission-llc-notice-of-application-and-establishing-intervention-deadline)
- [2026-12228 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-06-18/pdf/2026-12228.pdf)

## Related
- [Previous: 2026-12227, Brookfield White Pine Hydro, LLC; Notice of Revised Schedule for Environmental…](https://policyrisk.com/federal-register/2026-12227)
- [Next: 2026-12229, Texas Eastern Transmission, LP; Notice of Schedule for the Preparation of An En…](https://policyrisk.com/federal-register/2026-12229)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-12228 (as of 2026-06-25).