# 2026-13880: Pipeline Seeks Public Input on Desert Expansion

2026-13880, Transwestern Pipeline Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Planned Desert Southwest Expansion Project, and Notice of Public Scoping Sessions, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-07-09; PRIA reads it as touching household money (as of 2026-07-16).

- Canonical: https://policyrisk.com/federal-register/2026-13880
- As of: 2026-07-16
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-13880
- Title: Transwestern Pipeline Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Planned Desert Southwest Expansion Project, and Notice of Public Scoping Sessions
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 42431
- Published: 2026-07-09
- Effective: unknown
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-07-16

## In one line

Pipeline Seeks Public Input on Desert Expansion

## Summary

Transwestern Pipeline Company plans to expand its pipeline in Texas, New Mexico, and Arizona, and the government wants your thoughts on how this might affect the environment. They’re asking for public comments by August 5, 2026, to help decide if the project should move forward. This is your chance to speak up about possible changes and how they might impact local communities and nature.

## Effects PRIA read

- Landowners: Easements and Eminent Domain Risk: cost, high. If you own land near the planned route, Transwestern may contact you to negotiate an easement to build and operate the pipeline. You do not have to agree, but if the Commission approves the project the company could start court condemnation (eminent domain) proceedings and a judge would determine c…
- Large Construction Footprint Across Three States: cost, high. The project would build a 48-inch mainline stretching 526.5 miles plus 181.5 miles of laterals, new compressor stations, and meter stations, using a 150-foot-wide construction right-of-way for the mainline and 75–90 feet for laterals. Construction will require temporary construction workspace and s…
- Possible Environmental Effects to Local Areas: cost, medium. FERC will study environmental effects the project could cause, including water use and effects on aquifers, safety and emergency response, light pollution, impacts to wilderness areas and the San Pedro River Valley, threatened and endangered species and migratory birds, and cultural resources. Thes…
- More Natural Gas Capacity to NM and AZ: benefit, medium. Transwestern says the expansion would provide firm transportation of up to 2.3 billion cubic feet per day (Bcf/d) of natural gas from the Permian Basin to customers in New Mexico and Arizona and would upgrade the Phoenix Lateral for bi-directional flow. The company states the project is meant to se…
- You Can Comment — Deadline and Scoping Sessions: benefit, low. The public can submit written or oral comments to FERC; comments must be received by 5:00 p.m. Eastern Time on August 5, 2026. In-person scoping sessions are scheduled July 21–30, 2026 at listed Arizona and New Mexico locations, and virtual sessions are scheduled July 30, 2026 (6:00–8:00 p.m. MDT)…
- Right to Intervene After Formal Application: benefit, low. Once Transwestern files a formal application, members of the public may seek intervenor status. Only intervenors are official parties who can request rehearing of FERC’s decision and be heard in court on appeals of the Commission’s final ruling.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-13880 on federalregister.gov](https://www.federalregister.gov/documents/2026/07/09/2026-13880/transwestern-pipeline-company-llc-notice-of-scoping-period-requesting-comments-on-environmental)
- [2026-13880 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-07-09/pdf/2026-13880.pdf)

## Related
- [Previous: 2026-13879, Agency Information Collection Activities: Submission for OMB Review; Comment Re…](https://policyrisk.com/federal-register/2026-13879)
- [Next: 2026-13881, GR Catalyst Two, LLC ; Notice of Revised Procedural Schedule](https://policyrisk.com/federal-register/2026-13881)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-13880 (as of 2026-07-16).