## Facts
- Document number: 2026-19201
- Title: Southern Star Central Gas Pipeline, Inc.; Notice of Application and Establishing Intervention Deadline
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 59127
- Published: 2026-09-18
- Effective: unknown
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-09-25

## In one line

$75M Gas Boost for Kansas Power Plant Pipeline Push

## Summary

Southern Star Central Gas Pipeline wants to build new pipeline and compressor stations in Kansas to deliver more natural gas to the Evergy McNew Power Plant. This $75.5 million project aims to boost gas flow by 123,000 dekatherms daily, helping power up the region. If you’re interested, you’ve got until a set deadline to speak up or get involved!

## Effects PRIA read

- File Comments or Intervene by Oct 6: benefit, low. You can file comments, protests, or a motion to intervene in FERC Docket CP26-572-000. There is no fee to file, and the deadline to file a motion to intervene or submit comments or protests is 5:00 p.m. Eastern Time on October 6, 2026.
- Intervenor Status Gives Legal Rights: benefit, medium. If you file a timely motion to intervene you become a party to the proceeding and only intervenors have the right to request rehearing of Commission orders and to challenge those orders in the U.S. Circuit Courts of Appeal. To obtain party status you must file your motion to intervene by 5:00 p.m.…
- Commenters Added to Environmental Mailing List: benefit, low. People who comment on the project's environmental review will be placed on the Commission's environmental mailing list and will receive notifications when the environmental assessment (EA) or environmental impact statement (EIS) is issued and when related meetings are scheduled. Submitting comments…
- 90-Day Environmental Review Timing Rule: mixed, medium. Within 90 days of this Notice, Commission staff will either complete its environmental review and place it in the public record or issue a Notice of Schedule for Environmental Review. If an EA or final environmental impact statement (FEIS) is issued, federal and state agencies have to complete requ…
- Project Scope, Capacity, and Cost Details: mixed, low. Southern Star proposes to build about 1.6 miles of 30-inch pipeline, a new Hutchinson Compressor Station with three compressor units totaling 5,700 horsepower, and one new meter station, plus ancillary changes in Harvey and Stafford Counties, Kansas. The Project is designed to provide approximately…

## Related documents

- [2026-20744](https://policyrisk.com/federal-register/2026-20744): Combined Notice of Filings #2, 2026-10-09
- [2026-20658](https://policyrisk.com/federal-register/2026-20658): Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, an…, 2026-10-08
- [2026-20659](https://policyrisk.com/federal-register/2026-20659): Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline, 2026-10-08
- [2026-20642](https://policyrisk.com/federal-register/2026-20642): Combined Notice of Filings, 2026-10-08
- [2026-20580](https://policyrisk.com/federal-register/2026-20580): Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonm…, 2026-10-08
- [2026-20582](https://policyrisk.com/federal-register/2026-20582): Combined Notice of Filings, 2026-10-08

## Sources
- [2026-19201 on federalregister.gov](https://www.federalregister.gov/documents/2026/09/18/2026-19201/southern-star-central-gas-pipeline-inc-notice-of-application-and-establishing-intervention-deadline)
- [2026-19201 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-09-18/pdf/2026-19201.pdf)

## Related
- [Previous: 2026-19200, Commission Information Collection Activities (Ferc-521); Comment Request; Exten…](https://policyrisk.com/federal-register/2026-19200)
- [Next: 2026-19202, Dauphin Island Gathering Partners; Notice of Scoping Period Requesting Comments…](https://policyrisk.com/federal-register/2026-19202)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-19201 (as of 2026-09-25).