## Facts
- Document number: 2026-20626
- Title: SMR, LLC; Palisades SMR, LLC; Pioneer Units 1 and 2; Phased Construction Permit Application-Limited Work Authorization
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 64409
- Published: 2026-10-08
- Effective: 2026-10-08
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-10-15

## In one line

Michigan's Mini Nukes: Permit Kickoff for Pioneer Reactors Begins

## Summary

Holtec’s Palisades SMR, LLC just kicked off the first step to build two new small nuclear reactors called Pioneer Units 1 and 2 in Michigan. The Nuclear Regulatory Commission is officially letting everyone know they got the application and a request to start some early work. This process starts in October 2026 and could speed up clean energy development while keeping safety front and center.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) is providing public notice each week, for four consecutive weeks, beginning October 1, 2026, of receipt and availability of the first part of a phased construction permit application, including a limited work authorization (LWA) request, from SMR, LLC, on behalf of Palisades SMR, LLC, a wholly-owned subsidiary of Holtec International (collectively, Holtec), for a dual-unit SMR-300 plant located at the Palisades Energy Center (PEC) in Covert, Michigan. The units are individually named Pioneer Unit 1 and Pioneer Unit 2. This is the second of four consecutive weekly notifications.

## Effects PRIA read

No economic effects identified for this document.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-20626 on federalregister.gov](https://www.federalregister.gov/documents/2026/10/08/2026-20626/smr-llc-palisades-smr-llc-pioneer-units-1-and-2-phased-construction-permit-application-limited-work)
- [2026-20626 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-10-08/pdf/2026-20626.pdf)

## Related
- [Previous: 2026-20625, Agency Information Collection Activities: Comment Request on the Burden Related…](https://policyrisk.com/federal-register/2026-20625)
- [Next: 2026-20627, National Register of Historic Places; Notification of Pending Nominations and R…](https://policyrisk.com/federal-register/2026-20627)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-20626 (as of 2026-10-15).