# 2026-22947: Hydropower Builder Asks Federal Regulators for More Time at Pennsylvania Dam

2026-22947, FFP Missouri 6, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, is a Federal Register notice from Energy Department, Federal Energy Regulatory Commission published 2026-11-12, effective Deadline for filing comments: December 7, 2026 5:00 p.m. Eastern Time. (as of 2026-11-12).

- Canonical: https://policyrisk.com/federal-register/2026-22947
- As of: 2026-11-12
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-22947
- Title: FFP Missouri 6, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
- Type: Notice
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 72862
- Published: 2026-11-12
- Effective: Deadline for filing comments: December 7, 2026 5:00 p.m. Eastern Time.
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-11-12

## In one line

Hydropower Builder Asks Federal Regulators for More Time at Pennsylvania Dam

## Summary

FFP Missouri 6, LLC asked for more time to start and finish building a hydroelectric project at the Emsworth Back Channel Dam in Pennsylvania. The government is now accepting public comments, protests, and requests to join the discussion until December 7, 2026. This extension could affect the project’s timeline but doesn’t mention any changes to costs yet.

## Effects PRIA read

No economic effects identified for this document.

## Related documents

- [2026-22879](https://policyrisk.com/federal-register/2026-22879): Combined Notice of Filings #1, 2026-11-10
- [2026-22878](https://policyrisk.com/federal-register/2026-22878): ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 2026-11-10
- [2026-22877](https://policyrisk.com/federal-register/2026-22877): Combined Notice of Filings, 2026-11-10
- [2026-22803](https://policyrisk.com/federal-register/2026-22803): Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Solic…, 2026-11-09
- [2026-22791](https://policyrisk.com/federal-register/2026-22791): Combined Notice of Filings, 2026-11-09
- [2026-22721](https://policyrisk.com/federal-register/2026-22721): Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Leidy Access Exp…, 2026-11-06

## Sources
- [2026-22947 on federalregister.gov](https://www.federalregister.gov/documents/2026/11/12/2026-22947/ffp-missouri-6-llc-notice-of-request-for-extension-of-time-to-commence-and-complete-construction)
- [2026-22947 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-11-12/pdf/2026-22947.pdf)

## Related
- [Previous: 2026-22946, International Falls Power Company; Notice of Scoping Period Requesting Comments…](https://policyrisk.com/federal-register/2026-22946)
- [Next: 2026-22949, GB Energy Park, LLC; Notice of Request for Extension of Time To Commence and Co…](https://policyrisk.com/federal-register/2026-22949)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-22947 (as of 2026-11-12).