## Facts
- Document number: 2026-23355
- Title: SMR, LLC; Palisades SMR, LLC; Pioneer Units 1 and 2; Receipt of Construction Permit Application
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 73817
- Published: 2026-11-17
- Effective: 2026-11-17
- Comments close: not stated
- Significant: no
- Touches household money: no
- Regulation identifier numbers: none
- Last updated: 2026-11-17

## In one line

Pioneer Units: Michigan’s small modular reactors enter another permit-review chapter

## Summary

SMR, LLC, through its subsidiary Palisades SMR, has submitted the second part of their construction permit application for two new small modular nuclear reactors called Pioneer Units 1 and 2 in Michigan. The Nuclear Regulatory Commission is sharing this update publicly starting November 10, 2026, as part of a four-week notice series. This project could bring new energy jobs and infrastructure, with important reviews and decisions happening soon.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) is providing public notice of receipt and availability each week, for four consecutive weeks, beginning November 10, 2026, of the second part of a phased construction permit application, from SMR, LLC, on behalf of Palisades SMR, LLC, a wholly-owned subsidiary of Holtec International, for a dual-unit SMR-300 plant located at the Palisades Energy Center (PEC) in Covert, Michigan. The units are individually named Pioneer Unit 1 and Pioneer Unit 2. This is the second of four consecutive weekly notifications. The application for the construction permits was received on September 30, 2026.

## Effects PRIA read

No economic effects identified for this document.

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-23355 on federalregister.gov](https://www.federalregister.gov/documents/2026/11/17/2026-23355/smr-llc-palisades-smr-llc-pioneer-units-1-and-2-receipt-of-construction-permit-application)
- [2026-23355 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-11-17/pdf/2026-23355.pdf)

## Related
- [Previous: 2026-23354, Loan Guaranty: Assistance to Eligible Individuals in Acquiring Specially Adapte…](https://policyrisk.com/federal-register/2026-23354)
- [Next: 2026-23356, Tribal Advisory Committee](https://policyrisk.com/federal-register/2026-23356)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-23355 (as of 2026-11-17).