# 2026-23521: EPA Weighs Texas Updates for Concrete Batch Plant Permits

2026-23521, Air Plan Approval; Texas; Revisions to Concrete Batch Plant Standard Permit, is a Federal Register proposed rule from Environmental Protection Agency published 2026-11-18, effective Written comments must be received on or before December 18, 2026.; PRIA reads it as touching household money (as of 2026-11-19).

- Canonical: https://policyrisk.com/federal-register/2026-23521
- As of: 2026-11-19
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-23521
- Title: Air Plan Approval; Texas; Revisions to Concrete Batch Plant Standard Permit
- Type: Proposed Rule
- Agencies: Environmental Protection Agency
- Citation: 91 FR 74143
- Published: 2026-11-18
- Effective: Written comments must be received on or before December 18, 2026.
- Comments close: 2026-12-18
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-19

## In one line

EPA Weighs Texas Updates for Concrete Batch Plant Permits

## Summary

The EPA is proposing to approve updates to Texas’ rules for concrete batch plants, which mix concrete in different ways. These changes affect businesses running these plants by updating their standard permits to keep air cleaner. If you want to share your thoughts, you have until December 18, 2026, to comment—no extra costs or fees are mentioned.

## Abstract

Pursuant to the Federal Clean Air Act (CAA or the Act), the Environmental Protection Agency (EPA) is proposing to approve revisions to the Texas State Implementation Plan (SIP) submitted by the Texas Commission on Environmental Quality (TCEQ) on April 2, 2026, to update the provisions for standard permits (SP) for concrete batch plants (CBP) that perform wet batching, dry batching, or central mixing.

## Effects PRIA read

- 8‑Year Review Could Trigger New Controls: cost, low. Texas will require the Texas Commission on Environmental Quality (TCEQ) to review the concrete batch plant standard permit at least once every eight years (new 30 TAC 116.605(d)(4)). The EPA says this review is intended to keep the permit ‘‘protective’’ of the National Ambient Air Quality Standards…
- Extensions/New Construction Must Meet Amended Permit: cost, low. New 30 TAC 116.605(f)(1) and (f)(2) let the TCEQ require operators authorized to begin new construction of permanent concrete batch plants to comply with an amended standard permit if the operator did not begin construction before the adoption of the amended permit and has filed an extension to beg…
- EPA Finds No Significant Small‑Business Impact: benefit, low. The EPA states this approval is ‘‘certified as not having a significant economic impact on a substantial number of small entities’’ under the Regulatory Flexibility Act. The Agency also says it does not impose additional requirements beyond State law.

## Related documents

- [2026-22082](https://policyrisk.com/federal-register/2026-22082): Additional Reconsideration Standards of Performance for New, Reconstructed, and Modified Sources and Emissions Guidelines for Existing Sour…, 2026-10-29
- [2026-21155](https://policyrisk.com/federal-register/2026-21155): Renewable Fuel Standard (RFS) Program: Reallocation of Additional 2025 Small Refinery Exemptions, 2026-10-16
- [2026-20849](https://policyrisk.com/federal-register/2026-20849): Clean Water Act Hazardous Substance Facility Response Plans: Compliance Date Delay and Changes To Reflect Administration Policy, 2026-10-13
- [2026-19072](https://policyrisk.com/federal-register/2026-19072): Rescission of the Greenhouse Gas Findings for Fossil Fuel-Fired Power Plants and Repeal of Regulations for Power Plant Greenhouse Gas Emiss…, 2026-09-17
- [2026-19071](https://policyrisk.com/federal-register/2026-19071): Partial Repeal of the Carbon Pollution Standards for Fossil Fuel-Fired Electric Generating Units, 2026-09-17
- [2026-18317](https://policyrisk.com/federal-register/2026-18317): Updated Definition of “Waters of the United States”, 2026-09-09

## Sources
- [2026-23521 on federalregister.gov](https://www.federalregister.gov/documents/2026/11/18/2026-23521/air-plan-approval-texas-revisions-to-concrete-batch-plant-standard-permit)
- [2026-23521 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-11-18/pdf/2026-23521.pdf)

## Related
- [Previous: 2026-23519, Air Plan Approval; Texas; Collin County Second 10-Year Maintenance Plan for the…](https://policyrisk.com/federal-register/2026-23519)
- [Next: 2026-23533, Racial Nondiscrimination in Private Schools; Hearing](https://policyrisk.com/federal-register/2026-23533)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-23521 (as of 2026-11-19).