# 2026-23630: New Mexico Uranium Project Seeks Two More Decades of Life

2026-23630, NuFuels, Inc.; Crownpoint Uranium Recovery Project; Draft Environmental Assessment and Draft Programmatic Agreement, is a Federal Register notice from Nuclear Regulatory Commission published 2026-11-20, effective Submit comments by December 21, 2026. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.; PRIA reads it as touching household money (as of 2026-11-20).

- Canonical: https://policyrisk.com/federal-register/2026-23630
- As of: 2026-11-20
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-23630
- Title: NuFuels, Inc.; Crownpoint Uranium Recovery Project; Draft Environmental Assessment and Draft Programmatic Agreement
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 75356
- Published: 2026-11-20
- Effective: Submit comments by December 21, 2026. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.
- Comments close: 2026-12-21
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-20

## In one line

New Mexico Uranium Project Seeks Two More Decades of Life

## Summary

NuFuels, Inc. wants to keep running its Crownpoint Uranium Recovery Project in New Mexico for 20 more years. The Nuclear Regulatory Commission is checking the environmental impact and asking the public to share their thoughts by December 21, 2026. This decision affects local communities and the environment, with potential changes in uranium recovery operations and long-term land use.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment a draft environmental assessment (EA) and finding of no significant impact (FONSI) and draft programmatic agreement (PA) regarding the proposed renewal of Source and Byproduct Materials License Number SUA-1580, which authorizes NuFuels, Inc., to operate the proposed Crownpoint Uranium Project (CUP) in situ recovery (ISR) facility. NuFuels requests a renewed license that, if granted, would authorize it to construct and operate the CUP for 20 years beyond the date of the renewed license. The CUP operations are proposed on four project areas in the Church Rock and Crownpoint areas of McKinley County, New Mexico (Church Rock Section 8, Church Rock Section 17, Unit 1, and Crownpoint).

## Effects PRIA read

- 20-Year License Could Allow ISR Operations: mixed, medium. If the Nuclear Regulatory Commission renews NuFuels' Source and Byproduct Materials License SUA-1580, NuFuels could construct and operate in situ recovery (ISR) uranium facilities on four project areas in the Church Rock and Crownpoint areas of McKinley County, New Mexico for 20 years beyond the da…
- Operational Limits on Flow and Production: benefit, low. The license would include explicit operational limits: the processing plant flow rate at each area (Church Rock, Unit 1, or Crownpoint) must not exceed 4,000 gallons per minute, and total yellowcake production must not exceed 3 million pounds annually.
- Groundwater Restoration and Decommissioning Requirements: benefit, medium. Before or after ISR wellfields cease operation, NuFuels must perform aquifer restoration to return groundwater quality within the production zone to standards consistent with NRC requirements and 10 CFR part 40, Appendix A, Criterion 5B(5), then submit a decommissioning plan for NRC approval and pr…

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-23630 on federalregister.gov](https://www.federalregister.gov/documents/2026/11/20/2026-23630/nufuels-inc-crownpoint-uranium-recovery-project-draft-environmental-assessment-and-draft)
- [2026-23630 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-11-20/pdf/2026-23630.pdf)

## Related
- [Previous: 2026-23629, Draft Revisions to Regulatory Issue Summary and Supplement: Use of EPRI/NEI Joi…](https://policyrisk.com/federal-register/2026-23629)
- [Next: 2026-23631, Take of Marine Mammals Incidental to Specified Activities; Taking Marine Mammal…](https://policyrisk.com/federal-register/2026-23631)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-23630 (as of 2026-11-20).