# 2026-23884: FERC Clarifies When Silence Becomes a Rehearing Request Denial

2026-23884, Denial of Rehearing Requests by Operation of Law Under the Commission's Rules of Practice and Procedure, is a Federal Register rule from Energy Department, Federal Energy Regulatory Commission published 2026-11-24, effective 2026-12-24; PRIA reads it as touching household money (as of 2026-11-24).

- Canonical: https://policyrisk.com/federal-register/2026-23884
- As of: 2026-11-24
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-23884
- Title: Denial of Rehearing Requests by Operation of Law Under the Commission's Rules of Practice and Procedure
- Type: Rule
- Agencies: Energy Department; Federal Energy Regulatory Commission
- Citation: 91 FR 75775
- Published: 2026-11-24
- Effective: 2026-12-24
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: 1902-AG51
- Last updated: 2026-11-24

## In one line

FERC Clarifies When Silence Becomes a Rehearing Request Denial

## Summary

The Federal Energy Regulatory Commission is updating its rules about rehearing requests. Now, if the Commission doesn’t respond within 30 days, the request is only denied for cases under the Federal Power Act and Natural Gas Act. This change kicks in on December 24, 2026, and mainly affects companies and individuals involved in energy regulation, helping clarify when they can move to court.

## Abstract

The Federal Energy Regulatory Commission (Commission) is revising its regulations addressing the circumstances under which a request for rehearing is denied absent Commission action within a particular time frame. Currently, the Commission's regulations provide that unless the Commission acts upon a request for rehearing within 30 days after the request is filed, the request is denied. As revised in this final rule, the regulation will apply only to matters subject to the rehearing and judicial review provisions in the Federal Power Act (FPA) and Natural Gas Act (NGA).

## Effects PRIA read

- 30‑day Deemed Denial: FPA and NGA Only: benefit, low. If you file a rehearing request under the Federal Power Act (FPA) or the Natural Gas Act (NGA), your request is treated as denied unless the Commission acts within 30 days. After that deemed denial, an aggrieved party may seek judicial review within the applicable 60‑day statutory window. This chan…
- ICA Cases No 30‑Day Deemed Denial: cost, low. For matters arising under the Interstate Commerce Act (ICA), Rule 713(f)'s 30‑day deemed denial no longer applies. Parties in ICA rehearing matters will receive notice of disposition through a Commission order rather than an automatic deemed denial after 30 days.
- No New Reporting or Small‑Entity Burden: benefit, low. The Commission states this final rule does not impose any new or different public reporting requirements and will not require utilities or natural gas companies to file new information. The Commission certifies under the Regulatory Flexibility Act that the rule will not have a significant economic…
- Notice Practice and Court Filing Protection: benefit, low. For FPA/NGA matters the Commission will continue issuing two types of 31st‑day notices (a simple denial‑by‑operation‑of‑law notice or a denial plus notice that the Commission will consider the matter further). The Commission also says it will not seek dismissal of petitions for review filed within…

## Related documents

- [2026-23833](https://policyrisk.com/federal-register/2026-23833): FERC Form 580 Interrogatories on Fuel and Energy Purchase Practices; Notice of Request for Partial Waiver, 2026-11-24
- [2026-23889](https://policyrisk.com/federal-register/2026-23889): The City of Columbus, Ohio; Notice of Intent To Prepare an Environmental Assessment, 2026-11-24
- [2026-23834](https://policyrisk.com/federal-register/2026-23834): Spire MoGas Pipeline LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 2026-11-24
- [2026-23883](https://policyrisk.com/federal-register/2026-23883): Combined Notice of Filings, 2026-11-24
- [2026-23890](https://policyrisk.com/federal-register/2026-23890): Bonneville Power Administration; Notice of Filing, 2026-11-24
- [2026-23891](https://policyrisk.com/federal-register/2026-23891): Enable Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 2026-11-24

## Sources
- [2026-23884 on federalregister.gov](https://www.federalregister.gov/documents/2026/11/24/2026-23884/denial-of-rehearing-requests-by-operation-of-law-under-the-commissions-rules-of-practice-and)
- [2026-23884 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-11-24/pdf/2026-23884.pdf)

## Related
- [Previous: 2026-23879, Airworthiness Directives; Airbus Helicopters](https://policyrisk.com/federal-register/2026-23879)
- [Next: 2026-23900, IFR Altitudes; Miscellaneous Amendments](https://policyrisk.com/federal-register/2026-23900)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-23884 (as of 2026-11-24).