# 2026-24075: Nuclear Waste Report Deadline Moves, Pending Research and a 2033 Backstop

2026-24075, Northern States Power Company; Prairie Island Independent Spent Fuel Storage Installation; License Amendment Application, is a Federal Register notice from Nuclear Regulatory Commission published 2026-11-27, effective 2027-01-26; PRIA reads it as touching household money (as of 2026-11-27).

- Canonical: https://policyrisk.com/federal-register/2026-24075
- As of: 2026-11-27
- Plain-text twin of the page above; the HTML and this file carry the same facts.

## Facts
- Document number: 2026-24075
- Title: Northern States Power Company; Prairie Island Independent Spent Fuel Storage Installation; License Amendment Application
- Type: Notice
- Agencies: Nuclear Regulatory Commission
- Citation: 91 FR 76799
- Published: 2026-11-27
- Effective: 2027-01-26
- Comments close: not stated
- Significant: no
- Touches household money: yes
- Regulation identifier numbers: none
- Last updated: 2026-11-27

## In one line

Nuclear Waste Report Deadline Moves, Pending Research and a 2033 Backstop

## Summary

Northern States Power Company wants to change a deadline for safety reports about storing spent nuclear fuel at Prairie Island in Minnesota. They’re asking to push back the first report due date from 2028 to either six months after a key research report comes out or 2033, whichever comes first. This affects local communities and regulators, with a chance to speak up by January 26, 2027.

## Abstract

The U.S. Nuclear Regulatory Commission (NRC) has received a license amendment application from Northern States Power Company (NSPM) for an amendment to Materials License No. SNM-2506 for the Prairie Island Independent Spent Fuel Storage Installation (PI ISFSI) located in Welch, Minnesota. The amendment request seeks to change License Condition 26. The subject License Condition depends, in part, on the completion of the joint Electric Power Research Institute (EPRI) and Department of Energy (DOE) "High Burnup Dry Storage Cask Research and Development Project" (HDRP). License Condition 26 includes two requirements to provide evaluations to the NRC by specified due dates. Due to the change in the timeline for completing the evaluations from the HDRP initial period of storage, NSPM proposes to revise License Condition 26 to modify the due date of the first of these evaluations from April 4, 2028, to within six months of the HDRP initial storage period report publication date or April 4, 2033, whichever is earlier.

## Effects PRIA read

- Safety-report deadline pushed back: cost, low. Northern States Power Company asked to change the first required safety evaluation deadline for high-burnup spent fuel at the Prairie Island ISFSI from April 4, 2028, to either within six months after the EPRI/DOE High Burnup Dry Storage Cask Research and Development Project (HDRP) initial storage…
- Deadline to request a hearing: benefit, low. Anyone whose interest may be affected can request a hearing or petition to intervene in the NRC process, but petitions must be filed by January 26, 2027 (60 days after this notice's publication).

## Related documents

- [2026-19568](https://policyrisk.com/federal-register/2026-19568): Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight, 2026-09-24
- [2026-14341](https://policyrisk.com/federal-register/2026-14341): Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, 2026-07-16
- [2026-13687](https://policyrisk.com/federal-register/2026-13687): Implementation of the National Environmental Policy Act, 2026-07-07
- [2026-12067](https://policyrisk.com/federal-register/2026-12067): Fee Schedules; Fee Recovery for Fiscal Year 2026, 2026-06-16
- [2026-08550](https://policyrisk.com/federal-register/2026-08550): Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles, 2026-05-01
- [2026-08015](https://policyrisk.com/federal-register/2026-08015): Generic Environmental Impact Statement for Licensing of New Nuclear Reactors, 2026-04-24

## Sources
- [2026-24075 on federalregister.gov](https://www.federalregister.gov/documents/2026/11/27/2026-24075/northern-states-power-company-prairie-island-independent-spent-fuel-storage-installation-license)
- [2026-24075 as published (PDF)](https://www.govinfo.gov/content/pkg/FR-2026-11-27/pdf/2026-24075.pdf)

## Related
- [Previous: 2026-24074, 60-Day Notice of Proposed Information Collection: Housing Opportunities for Per…](https://policyrisk.com/federal-register/2026-24074)
- [Next: 2026-24076, Extending Deadlines for Submissions by Importers of Automobiles Qualifying for…](https://policyrisk.com/federal-register/2026-24076)
- [All Federal Register documents](https://policyrisk.com/federal-register)

Source: PRIA, https://policyrisk.com/federal-register/2026-24075 (as of 2026-11-27).