2025-18993Notice

Pipeline Giants Team Up for Billion-Dollar Gas Boost in Mississippi

Published Date: 9/30/2025

Notice

Summary

Gulf South Pipeline and Texas Gas Transmission want to build new pipelines and compressor stations in Mississippi to boost natural gas flow by over 1 billion cubic feet daily. This $1.1 billion project will help big energy companies get more gas, while swapping some pipeline parts between the two companies. If you’re interested, you’ve got until a set deadline to speak up or get involved!

Analyzed Economic Effects

5 provisions identified: 4 benefits, 0 costs, 1 mixed.

Large pipeline build in Mississippi

Gulf South proposes to build the 103-mile, 36-inch Kosciusko Junction Pipeline and an 8-mile, 36-inch Columbia Gulf Lateral, plus multiple compressor stations and appurtenances in Attala, Clarke, Holmes, Humphreys, Jasper, Leake, Newton, and Sunflower Counties, Mississippi. The Project would create about 1.175 billion cubic feet per day (Bcf/d) of new capacity (1.1 Bcf/d subscribed to Southern Company Services, Florida Power & Light Company, and PowerSouth Energy Cooperative) and Gulf South estimates the Project cost at $1,031,400,000.

Clean Water Act Section 401 requirement

The Applicants state that a water quality certification under Section 401 of the Clean Water Act is required from the Mississippi Department of Environmental Quality for the Project. The Applicants are instructed to submit to the Commission the request for certification date and either the certifying agency's decision or evidence of waiver when available.

Texas Gas asset transfer and remaining shippers' capacity

Texas Gas proposes to sell the Greenville Lateral, Isola Compressor Station, and appurtenances to Gulf South, to install a 20,952 horsepower compressor at its Greenville CS, to abandon 420,000 Dth/d of mainline capacity to Gulf South by lease, and to acquire 595,000 Dth/d of capacity from Gulf South by lease; the Project will allow Texas Gas to transport up to 595,000 dekatherms per day (Dth/d) to the remaining shippers on the Greenville Lateral. Texas Gas estimates its Project cost at $79.5 million.

Free public participation deadline

You can file comments, protests, or a motion to intervene in the FERC dockets for this project at no cost. The deadline to file a motion to intervene or submit comments or protests is 5:00 p.m. Eastern Time on October 16, 2025; filings can be made via FERC eComment, eFiling, or by paper mail, and FERC staff will assist with eFiling.

90-day environmental review schedule rule

Within 90 days of this Notice, FERC staff will either complete its environmental review and place it in the public record or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule is issued, it will indicate milestones and anticipated dates for the Final Environmental Impact Statement (FEIS) or Environmental Assessment (EA), and federal and state agencies will be notified to complete necessary federal authorizations within 90 days after issuance of the FEIS or EA.

Your PRIA Score

Score Hidden

Personalized for You

How does this regulation affect your finances?

Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.

Free to start

Key Dates

Published Date
Effective Date
9/30/2025
10/16/2025

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML
Back to Federal Register

Take It Personal

Get Your Personalized Policy View

Start a Free Government Policy Watch to see how policy affects your household, then upgrade to PRIA Full Coverage for year-round monitoring.

Already have an account? Sign in