Southern Nuclear wants to delay a planned change at Vogtle Plant Unit 3 for one refueling cycle. This affects the plant’s operations in Georgia but won’t cause any safety risks. People have until March 25, 2026, to share their thoughts and until April 24, 2026, to ask for a hearing.

Analyzed Economic Effects

1 provisions identified: 1 benefits, 0 costs, 0 mixed.

Vogtle Unit 3 safety-change delayed

If you live in Georgia near Vogtle Unit 3, the plant owner wants to delay implementing Amendment No. 203 for one refueling cycle. Amendment No. 203 (issued August 8, 2025) was to be implemented before startup from the Spring 2026 refueling outage but the licensee asks to move the required implementation to before startup from the Fall 2027 refueling outage. The NRC proposes this delay involves no significant hazards consideration; comments are due March 25, 2026 and hearing requests are due April 24, 2026.

Your PRIA Score

Score Hidden

Personalized for You

How does this regulation affect your finances?

Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.

Free to start

Key Dates

Published Date
Comments Due
2/23/2026
3/25/2026

Department and Agencies

Department
Independent Agency
Agency
Nuclear Regulatory Commission
Source: View HTML
Back to Federal Register

Take It Personal

Get Your Personalized Policy View

Start a Free Government Policy Watch to see how policy affects your household, then upgrade to PRIA Full Coverage for year-round monitoring.

Already have an account? Sign in