Title 43Public LandsRelease 119-73

§390g–5 Authorization of appropriations to carry out phase II

Title 43 › Chapter CHAPTER 12— - RECLAMATION AND IRRIGATION OF LANDS BY FEDERAL GOVERNMENT › Subchapter SUBCHAPTER I— - GENERAL PROVISIONS › § 390g–5

Last updated Apr 6, 2026|Official source

Summary

Money is set aside to carry out Phase II: $31,000,000 (measured in October 1990 price levels) for fiscal years that begin after September 30, 1983. That sum can be increased or decreased to reflect normal changes in construction costs using the appropriate engineering cost indexes. The money will be given to individual projects in amounts the Secretary finds are feasible based on project studies.

Full Legal Text

Title 43, §390g–5

Public Lands — Source: USLM XML via OLRC

There is authorized to be appropriated for fiscal years beginning after September 30, 1983, $31,000,000 (October 1990 price levels) plus or minus such amounts, if any, as may be required by reason of ordinary fluctuations in construction costs as indicated by engineering cost indexes applicable to the type of construction involved herein to carry out phase II. Amounts shall be made available pursuant to the authorization contained in this section in sums for individual projects based on findings of feasibility by the Secretary.

Legislative History

Notes & Related Subsidiaries

Editorial Notes

Amendments

1992—Pub. L. 102–575 substituted “$31,000,000 (October 1990 price levels) plus or minus such amounts, if any, as may be required by reason of ordinary fluctuations in

Construction

costs as indicated by engineering cost indexes applicable to the type of

Construction

involved herein” for “$20,000,000 (October 1983 price levels)”.

Reference

Citations & Metadata

Citation

43 U.S.C. § 390g–5

Title 43Public Lands

Last Updated

Apr 6, 2026

Release point: 119-73