$61M Pipeline Upgrade Proposed for Washington Gas Flow
Published Date: 3/20/2025
Notice
Summary
Northwest Pipeline wants to buy and upgrade the Kelso-Beaver Pipeline from Portland General Electric and others. They plan to add a powerful compressor station in Washington to boost gas flow both ways, costing about $61 million. If approved, this will increase pipeline capacity and could affect gas rates, with a deadline soon for people to get involved.
Analyzed Economic Effects
3 provisions identified: 1 benefits, 1 costs, 1 mixed.
Buy and upgrade Kelso‑Beaver pipeline
Northwest Pipeline filed to buy the 18-mile, 20-inch Kelso-Beaver Pipeline and immediately add a new 5,500 horsepower compressor station in Cowlitz County, Washington to make the line bi-directional. The Project would add 52,400 Dth/day of firm westbound capacity and 131,000 Dth/day of firm eastbound capacity and is estimated to cost $60,800,979.
Proposal to charge TFL‑1 reservation rates
As part of the Project, Northwest proposes to charge TFL-1 incremental recourse reservation rates for the firm lateral transportation service associated with the expansion.
How to comment or intervene (deadline)
You can file comments, protests, or a motion to intervene with no fee; the deadline to file a motion to intervene is 5:00 p.m. Eastern Time on April 3, 2025. Intervenors become parties with the right to request rehearing of Commission orders and to challenge them in court.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20744, Combined Notice of Filings #2
The Federal Energy Regulatory Commission got a new filing from Iroquois Gas Transmission about changing their natural gas rates starting November 1, 2026. This affects customers and companies using their pipeline, who might see new negotiated prices. If you want to speak up or get involved, you have until October 19, 2026, to file your comments or protests.
2026-20658, Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents
The Shoshone Irrigation District missed the deadline to say if they want to renew their license for the Garland Canal hydro project in Wyoming, which ends in 2031. Because of this, they’re treated as if they don’t plan to relicense, opening the door for others to step in and apply. If you’re interested, now’s the time to file your intent and get your paperwork ready!
2026-20659, Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline
Eastern Shore Natural Gas is planning a big upgrade to its pipelines in Pennsylvania, Delaware, and Maryland, including building new loops and replacing old pipes. This $75 million project will boost gas delivery for local utilities and customers, with new facilities and some old parts being removed. If you want to have a say, you need to act before the intervention deadline set by the Federal Energy Regulatory Commission.
2026-20642, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new filing from Colorado Interstate Gas Company about changing a gas pipeline agreement that starts November 16, 2026. People who want to speak up or join the discussion must do so by October 14, 2026. This could affect gas rates and contracts, so keep an eye on the deadline if you’re involved!
2026-20580, Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonment and Capacity Replacement Project and Northern Lights 2027 Expansion Project
Northern Natural Gas Company plans to retire old pipeline sections in Iowa and Minnesota and build new ones to keep gas flowing smoothly and add extra capacity. This project will affect local communities and the environment but aims to do so responsibly, with a decision expected after public comments by November 2, 2026. The upgrades will help deliver more natural gas reliably, supporting energy needs without major environmental harm.
2026-20582, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and agreements that could affect how much customers pay starting this fall. If you want to speak up or get involved, you need to comment by mid-October or late October depending on the case. These updates impact pipeline rates and contracts, so keep an eye on deadlines to have your say!
Previous / Next Documents
Previous: 2025-04701, Boise-Kuna, Nampa & Meridian, Wilder and Big Bend Irrigation Districts; Notice of Intent To File License Application, Filing of Pre-Application Document (Pad), Commencement of ILP Pre-Filing Process and Scoping, Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests
The Boise-Kuna, Nampa & Meridian, Wilder, and Big Bend Irrigation Districts are starting the process to renew their license for the Lucky Peak Hydroelectric Project on the Boise River. This means they’re asking for public input and planning studies to make sure the project runs smoothly and protects the environment. If you live nearby or care about the river, now’s the time to share your thoughts before the official application is filed later this year.
Next: 2025-04704, Operations Notice for the Expansion of the Moving to Work Demonstration Program Technical Revisions
HUD is making some small technical updates to the rules for expanding the Moving to Work program, which helps public housing agencies try new ways to support residents. These tweaks don’t change the program’s goals or funding but keep everything running smoothly as more agencies join. The changes take effect on March 20, 2025, so agencies can keep moving forward without a hitch.