The Federal Energy Regulatory Commission got a bunch of new filings from natural gas pipeline companies about their rates and refunds. These changes mostly affect pipeline customers and shippers, with new rates and agreements kicking in April and May 2025. If you want to have your say, comments are due by April 14, 2025, so don’t miss out!
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
New Pipeline Rates and Agreements Start April–May 2025
A series of natural gas pipeline filings propose new negotiated rates, tariff changes, and other agreements that list effective dates of April 1, 2025 and May 1, 2025. These filings are directed at pipeline customers and shippers and may change the terms they pay or receive under existing contracts.
You Can Comment or Intervene by April 14, 2025
If you want to protest, comment, or intervene in any of these proceedings, you must file by 5:00 p.m. Eastern on April 14, 2025. The notice says intervention is required to become a party, and the Commission's Office of Public Participation can help landowners, community organizations, Tribal members, and others make filings or access information.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-20744, Combined Notice of Filings #2
The Federal Energy Regulatory Commission got a new filing from Iroquois Gas Transmission about changing their natural gas rates starting November 1, 2026. This affects customers and companies using their pipeline, who might see new negotiated prices. If you want to speak up or get involved, you have until October 19, 2026, to file your comments or protests.
2026-20658, Shoshone Irrigation District; Notice of Existing Licensee's Failure To File a Timely Notice of Intent To File a New License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents
The Shoshone Irrigation District missed the deadline to say if they want to renew their license for the Garland Canal hydro project in Wyoming, which ends in 2031. Because of this, they’re treated as if they don’t plan to relicense, opening the door for others to step in and apply. If you’re interested, now’s the time to file your intent and get your paperwork ready!
2026-20659, Eastern Shore Natural Gas Company; Notice of Application and Establishing Intervention Deadline
Eastern Shore Natural Gas is planning a big upgrade to its pipelines in Pennsylvania, Delaware, and Maryland, including building new loops and replacing old pipes. This $75 million project will boost gas delivery for local utilities and customers, with new facilities and some old parts being removed. If you want to have a say, you need to act before the intervention deadline set by the Federal Energy Regulatory Commission.
2026-20642, Combined Notice of Filings
The Federal Energy Regulatory Commission got a new filing from Colorado Interstate Gas Company about changing a gas pipeline agreement that starts November 16, 2026. People who want to speak up or join the discussion must do so by October 14, 2026. This could affect gas rates and contracts, so keep an eye on the deadline if you’re involved!
2026-20580, Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Ventura to Farmington A-Line Abandonment and Capacity Replacement Project and Northern Lights 2027 Expansion Project
Northern Natural Gas Company plans to retire old pipeline sections in Iowa and Minnesota and build new ones to keep gas flowing smoothly and add extra capacity. This project will affect local communities and the environment but aims to do so responsibly, with a decision expected after public comments by November 2, 2026. The upgrades will help deliver more natural gas reliably, supporting energy needs without major environmental harm.
2026-20582, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and agreements that could affect how much customers pay starting this fall. If you want to speak up or get involved, you need to comment by mid-October or late October depending on the case. These updates impact pipeline rates and contracts, so keep an eye on deadlines to have your say!
Previous / Next Documents
Previous: 2025-05914, Succession Plan for the FMCS
The Federal Mediation and Conciliation Service (FMCS) just announced a clear backup plan for who takes charge if the Director can’t do their job. Starting April 7, 2025, five top officials are lined up to step in, making sure FMCS keeps running smoothly with no interruptions. This plan affects FMCS staff and helps avoid any leadership confusion, with no extra costs involved.
Next: 2025-05917, Spire Storage West, LLC; Notice of Request for Extension of Time
Spire Storage West, LLC asked for more time—until May 19, 2028—to finish building their Clear Creek Expansion Project in Wyoming. Bad weather and supply chain problems slowed them down, so they can’t meet the original May 2025 deadline. This affects local energy infrastructure and could delay when the project starts making an impact.